5016 N CASPAR AVE 90041

Certificate Information: 5016 N CASPAR AVE 90041

Application / Permit
19016-20000-30783
Plan Check / Job No.
B19VN16505
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
INTERIOR REMODEL TO (E) CHURCH ACTIVITY CENTER AND ADD NEW ADA TOILET, RAMP AND ELEVATOR PER ENGINEERING.
Permit Issued
Issued on 1/7/2020
Issuing Office
Metro
Current Status
Permit Finaled on 2/27/2021

Permit Application Status History

Submitted 9/26/2019 APPLICANT
Disabled Access Plans Picked Up 10/9/2019 APPLICANT
Green Plans Picked Up 10/9/2019 APPLICANT
Assigned to Plan Check Engineer 10/11/2019 ARTIN ZARUKIAN
Corrections Issued 10/13/2019 ARTIN ZARUKIAN
Quality Review Completed 10/17/2019 GUANG MIN TUNG
Building Plans Picked Up 10/18/2019 APPLICANT
Plan Check Approved 12/23/2019 ARTIN ZARUKIAN
Issued 1/7/2020 LADBS
Permit Finaled 2/26/2021 RONALD PACHECO

Permit Application Clearance Information

Green Code Cleared 11/26/2019 AARON COSTA
DAS Clearance Cleared 11/27/2019 NORLITO MEDRANO
Grading Pre-Inspection Cleared 12/23/2019 ARTIN ZARUKIAN

Contact Information

Architect Kerr,, Robert E; Lic. No.: C28038 2551 S BUNDY DRIVE      LOS ANGELES, CA 90064
Contractor Vancrest Construction Corp; Lic. No.: 393800-B 7171 NORTH FIGUEROA STREET      LOS ANGELES, CA 90042
Engineer Smith,, Bradley Warren; Lic. No.: S2842 PO BOX 1064      OJAI, CA 93024

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2020 Partial Approval RONALD PACHECO
Deputy Drilled-In Anchors 3/2/2020 Conditional Approval RONALD PACHECO
Footing/Foundation/Slab 3/4/2020 Partial Approval RONALD PACHECO
Footing/Foundation/Slab 3/13/2020 Approved RONALD PACHECO
Wood Frame 4/21/2020 Approved RONALD PACHECO
Insulation 4/24/2020 Approved RONALD PACHECO
Wood Frame 4/30/2020 Approved RONALD PACHECO
Drywall Nailing 5/5/2020 Partial Approval RONALD PACHECO
Drywall Nailing 5/14/2020 Approved RONALD PACHECO
Footing/Foundation/Slab 6/8/2020 Partial Approval RONALD PACHECO
T-Bar Ceiling 7/13/2020 Approved LANNY MERRICK
Final 2/4/2021 Not Ready for Inspection RONALD PACHECO
Green Building Final 2/4/2021 Approved RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 2/4/2021 SGSOV Approved RONALD PACHECO
Smoke Detectors 2/4/2021 Approved RONALD PACHECO
Final 2/26/2021 Permit Finaled RONALD PACHECO