2590 S MIDVALE AVE 90064
Certificate Information: 2590 S MIDVALE AVE 90064
- Application / Permit
- 19016-20000-30400
- Plan Check / Job No.
- B19VN16265
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (38' X 31'-8") IRREGULAR SHAPED PORTION OF (E) DETACHED GARAGE AND STORAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229 PER ENGINEERING.
- Permit Issued
- Issued on 6/16/2020
- Issuing Office
- Current Status
- CofO Issued on 7/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2019 | RAPHAEL ROSAS |
| Corrections Issued | 9/24/2019 | RAPHAEL ROSAS |
| Building Plans Picked Up | 10/2/2019 | APPLICANT |
| Issued | 6/16/2020 | APPLICANT |
| CofO in Progress | 7/2/2021 | KENNETH NAGLE |
| Permit Finaled | 7/2/2021 | KENNETH NAGLE |
| CofO Issued | 7/2/2021 | KENNETH NAGLE |
| Permit Finaled | 7/2/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/2/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/2/2019 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 4/30/2020 | WALTER RAMIREZ |
| Address approval | Cleared | 5/20/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 6/9/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Metropolis Drafting And Construction Inc; Lic. No.: 930380-B | 13636 VENTURA BLVD 612 SHERMAN OAKS, CA 91423 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/16/2020 | Conditional Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/17/2020 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 9/17/2020 | Not Ready for Inspection | EVAN COOPER |
| Gas Test | 9/17/2020 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 9/17/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 9/17/2020 | Not Ready for Inspection | EVAN COOPER |
| Pre-Inspection | 9/17/2020 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 9/30/2020 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 9/30/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Gas Test | 9/30/2020 | Partial Approval | KENNETH NAGLE |
| HVAC-Rough | 9/30/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Sewer | 9/30/2020 | Approved | KENNETH NAGLE |
| ELECTRICAL-Rough | 10/9/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/9/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 10/9/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 10/9/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/9/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Sewer | 10/9/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 10/9/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/14/2020 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 10/14/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 10/14/2020 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/14/2020 | Approved | OGANES TARAKHCHYAN |
| Sewer | 10/14/2020 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/16/2020 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/16/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 10/16/2020 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/5/2020 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/5/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/12/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 11/12/2020 | Partial Approval | EVAN COOPER |
| Shower Pan | 11/12/2020 | Approved | EVAN COOPER |
| Insulation | 11/18/2020 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/1/2020 | Approved | RICHARD ROBLES |
| ELECTRICAL-Final | 3/22/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Service/Power Release | 3/22/2021 | Corrections Issued | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 3/24/2021 | Approved | KENNETH NAGLE |
| Service/Power Release | 3/24/2021 | Approved | KENNETH NAGLE |
| Final | 5/12/2021 | Corrections Issued | EVAN COOPER |
| Green Building Final | 5/12/2021 | Approved | EVAN COOPER |
| HVAC-Final | 5/12/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 5/12/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 5/12/2021 | Approved | EVAN COOPER |
| Final | 5/27/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 6/22/2021 | Conditional Approval | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 6/22/2021 | SGSOV Approved | JUAN VALENZUELA |