14735 W LASSEN ST 91345

Certificate Information: 14735 W LASSEN ST 91345

Application / Permit
19016-20000-30327
Plan Check / Job No.
B19VN16224
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' x 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP. BUILDING SHALL BE EQUIPPED WITH AUTOMATIC FIRE SPRINKLER SYSTEM.
Permit Issued
Issued on 1/30/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2019 APPLICANT
Assigned to Plan Check Engineer 9/23/2019 ROSENDO MEDINA
Corrections Issued 9/26/2019 ROSENDO MEDINA
Building Plans Picked Up 9/30/2019 APPLICANT
Plan Check Approved 1/30/2020 ROSENDO MEDINA
Issued 1/30/2020 LADBS
CofO in Progress 2/14/2022 JENNIFER RABUCHIN
Permit Finaled 4/4/2022 RONALD MYRICK
Permit Finaled 4/4/2022 RONALD MYRICK
CofO Issued 4/4/2022 RONALD MYRICK

Permit Application Clearance Information

Construction near power lines Cleared 11/6/2019 RIDWAN HARDY
Address approval Cleared 11/18/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 11/18/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 11/18/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 1/29/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/3/2021 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 3/3/2021 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 3/11/2021 Approved JENNIFER RABUCHIN
Sewer 3/11/2021 Corrections Issued JENNIFER RABUCHIN
Sewer 4/8/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/24/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/24/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/24/2021 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/24/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/3/2021 Conditional Approval MICHEL ABAJAN
ELECTRICAL-Rough 6/3/2021 Approved MICHEL ABAJAN
Green Building Rough 6/3/2021 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 6/3/2021 Approved MICHEL ABAJAN
Insulation 6/9/2021 Partial Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 6/18/2021 Partial Approval ARTHUR SARGSYAN
Green Building Rough 6/18/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 6/30/2021 Approved MICHEL ABAJAN
Drywall Nailing 6/30/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/5/2021 Corrections Issued JENNIFER RABUCHIN
Final 10/5/2021 Corrections Issued JENNIFER RABUCHIN
Gas Test 10/5/2021 Approved JENNIFER RABUCHIN
Green Building Final 10/5/2021 Approved JENNIFER RABUCHIN
HVAC-Final 10/5/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/5/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/5/2021 Corrections Issued JENNIFER RABUCHIN
Final 10/8/2021 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 10/18/2021 Approved JENNIFER RABUCHIN
Final 10/18/2021 Partial Inspection JENNIFER RABUCHIN
PLUMBING-Final 10/18/2021 Approved JENNIFER RABUCHIN
Smoke Detectors 10/18/2021 Approved JENNIFER RABUCHIN
Final 2/15/2022 OK to Issue CofO JENNIFER RABUCHIN