2821 N WESTSHIRE DR 90068

Certificate Information: 2821 N WESTSHIRE DR 90068

Application / Permit
19016-20000-29771
Plan Check / Job No.
B19VN15899
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NONSTRUCT INT REMODEL - REMODEL EXISTING TWO BEDRMS & BATH. ADD LAUNDRY RM. CONVERT EX LAUNDRY RM INTO BATHRM. ALL WORK WITHIN THE LOWER LEVEL OF EX 2-STORY SFD W/ ATT GAR. CLOSE UP EXISTING WINDOWS PER PLAN.
Permit Issued
Issued on 6/29/2021
Issuing Office
Current Status
Permit Finaled on 9/17/2021

Permit Application Status History

Submitted 9/18/2019 APPLICANT
Assigned to Plan Check Engineer 9/18/2019 HAYATO TSUCHIYA
Corrections Issued 9/18/2019 HAYATO TSUCHIYA
Plan Check Approved 9/18/2019 RAPHAEL ROSAS
Issued 6/29/2021 APPLICANT
Permit Finaled 9/17/2021 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 9/18/2019 MARITZA PRZEKOP

Contact Information

Contractor Bonomo Development; Lic. No.: 669677-B 1523 LINDA COURT      SIMI VALLEY, CA 93065

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2021 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 7/28/2021 Partial Inspection RAUL BARAJAS
Rough-Elec/Plmb/HVAC 7/28/2021 Partial Approval RAUL BARAJAS
Shower Pan 7/28/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 7/30/2021 Approved BRIAN SULLIVAN
HVAC-Rough 7/30/2021 Partial Approval BRIAN SULLIVAN
Insulation 7/30/2021 Not Ready for Inspection BRIAN SULLIVAN
Drywall Nailing 8/4/2021 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 8/4/2021 Partial Approval BRIAN SULLIVAN
Shower Pan 8/4/2021 Not Ready for Inspection BRIAN SULLIVAN
Drywall Nailing 8/6/2021 Approved BRIAN SULLIVAN
HVAC-Rough 8/6/2021 Approved BRIAN SULLIVAN
Shower Pan 8/6/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 8/31/2021 Approved BRIAN SULLIVAN
Final 9/14/2021 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 9/14/2021 Approved BRIAN SULLIVAN
Final 9/17/2021 Permit Finaled RICHARD STEINBACH