1820 W 11TH ST 90006
Certificate Information: 1820 W 11TH ST 90006
- Application / Permit
- 19016-20000-29742
- Plan Check / Job No.
- B19VN15882
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) DUPLEX & (4) LIGHT HOUSEKEEPING INTO (N) 3-UNIT APARTMENT BUILDING & (4) LIGHT HOUSEKEEPING UNITS; REMODEL ALL (E) LIGHT HOUSEKEEPING UNITS @ 1ST FLOOR (NFPA-13R FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofO Issued on 12/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 9/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/7/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/8/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/15/2019 | APPLICANT |
| Plan Check Approved | 1/3/2020 | NILOOFAR MEHRAIN |
| Issued | 12/23/2020 | APPLICANT |
| CofO in Progress | 12/20/2023 | JEROME BLACKWOOD |
| CofO Issued | 12/20/2023 | ERNESTO CORRAL |
| Permit Finaled | 12/20/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2019 | THOMAS LANG |
| CPC | Cleared | 11/14/2019 | ANNA VAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 11/14/2019 | ROBERT DUFF |
| Project located in CRA area | Cleared | 11/14/2019 | GISELLE CORELLA |
| Roof/Waste drainage to street | Cleared | 11/14/2019 | THOMAS LANG |
| Sewer availability | Cleared | 11/14/2019 | THOMAS LANG |
| ZI | Cleared | 11/14/2019 | GISELLE CORELLA |
| ZI | Cleared | 11/14/2019 | GISELLE CORELLA |
| HPOZ | Cleared | 11/20/2019 | MAX LODER |
| ZI | Cleared | 11/20/2019 | MAX LODER |
| DAS Clearance | Cleared | 12/11/2019 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | One10 Solutions Inc; Lic. No.: 1065944-B | 7304 BEVERLY BLVD #133 LOS ANGELES, CA 90036 |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2021 | Partial Approval | DANIEL COLLINS |
| Wood Frame | 1/28/2021 | Corrections Issued | DANIEL COLLINS |
| Wood Frame | 3/16/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Insulation | 2/16/2022 | No Access for Inspection | TIMOTHY BUXTON |
| Insulation | 2/17/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 2/17/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Insulation | 2/25/2022 | Approved | TIMOTHY BUXTON |
| Wood Frame | 2/25/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 4/6/2022 | Approved | DARRYL ARNOLD |
| Final | 4/6/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Pre-Inspection | 4/6/2023 | Partial Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Approved | RAMAZANALI ALMASI |
| Final | 9/13/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Smoke Detectors | 9/13/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 10/19/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 10/25/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Smoke Detectors | 10/25/2023 | Corrections Issued | RAMAZANALI ALMASI |
| Final | 11/28/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Smoke Detectors | 11/28/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 12/11/2023 | OK to Issue CofO | JEROME BLACKWOOD |
| Smoke Detectors | 12/11/2023 | Approved | JEROME BLACKWOOD |