6605 W MARYLAND DR 90048

Certificate Information: 6605 W MARYLAND DR 90048

Application / Permit
19016-20000-29179
Plan Check / Job No.
B19VN15612
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 11/18/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2019 APPLICANT
Assigned to Plan Check Engineer 9/13/2019 ALDOUS CHIC
Corrections Issued 9/13/2019 ALDOUS CHIC
Plan Check Approved 11/12/2019 SARKIS HARABEDIAN
Issued 11/18/2019 LADBS
CofO in Progress 11/30/2020 EVAN COOPER
Permit Finaled 1/7/2021 KENNETH NAGLE
CofO Issued 1/7/2021 KENNETH NAGLE
Permit Finaled 1/7/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 9/18/2019 ADRIAN CASTRO
CPC Cleared 9/18/2019 MARITZA PRZEKOP
Eng Process Fee Ord 176,300 Cleared 9/18/2019 ADRIAN CASTRO
Sewer availability Cleared 9/18/2019 ADRIAN CASTRO
ZI Cleared 9/18/2019 MARITZA PRZEKOP
Construction near power lines Cleared 11/5/2019 RIDWAN HARDY

Contact Information

Contractor Go Green Remodeling Inc; Lic. No.: 966335-B 4221 WILSHIRE BLVD STE 312      LOS ANGELES, CA 90010

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 2/21/2020 Not Ready for Inspection EVAN COOPER
Rough-Elec/Plmb/HVAC 2/21/2020 Corrections Issued EVAN COOPER
Pre-Inspection 4/23/2020 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/4/2020 Corrections Issued EVAN COOPER
HVAC-Rough 5/4/2020 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 5/4/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 6/26/2020 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 6/26/2020 Approved EVAN COOPER
Green Building Rough 6/26/2020 Approved EVAN COOPER
METHANE-Rough 6/26/2020 Approved EVAN COOPER
Drywall Nailing 7/16/2020 Corrections Issued KENNETH NAGLE
Drywall Nailing 7/31/2020 Approved EVAN COOPER
Insulation 7/31/2020 Approved EVAN COOPER
Special/Order Compliance 7/31/2020 Approved EVAN COOPER
Drywall Nailing 8/14/2020 Approved EVAN COOPER
Shower Pan 8/14/2020 Approved EVAN COOPER
Final 10/29/2020 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/29/2020 SGSOV Not Ready EVAN COOPER
BUILDING-Rough-Frame 11/5/2020 Approved EVAN COOPER
ELECTRICAL-Final 11/5/2020 Approved EVAN COOPER
Final 11/5/2020 Corrections Issued EVAN COOPER
Green Building Final 11/5/2020 Approved EVAN COOPER
HVAC-Final 11/5/2020 Approved EVAN COOPER
PLUMBING-Final 11/5/2020 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 11/5/2020 SGSOV Approved EVAN COOPER
Smoke Detectors 11/5/2020 Approved EVAN COOPER
Enclosure/Fence 11/30/2020 Approved EVAN COOPER
Final 11/30/2020 Conditional Approval EVAN COOPER