2959 S KELTON AVE 90064

Certificate Information: 2959 S KELTON AVE 90064

Application / Permit
19016-20000-28346
Plan Check / Job No.
B19VN15168
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC - INT. REMODEL: REMOVE WALL BETWEEN EX DINING RM & KITCHEN, CONVERT EX LAUNDRY RM INTO BATHRM & CONVERT EX CABINET NICHE INTO WASHER/DRYER PER PLAN. THIS PERMIT TO INCLUDE KITCHEN & EX BATHRM REMODEL.
Permit Issued
Issued on 9/15/2020
Issuing Office
Current Status
Permit Finaled on 8/5/2021

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/6/2019 HAYATO TSUCHIYA
Corrections Issued 9/6/2019 HAYATO TSUCHIYA
Building Plans Picked Up 9/11/2019 APPLICANT
Plan Check Approved 11/19/2019 HAYATO TSUCHIYA
Issued 9/15/2020 APPLICANT
Permit Finaled 8/4/2021 KENNETH NAGLE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/10/2019 TIMOTHY POWELL

Contact Information

Contractor Mc Burney Matthew Construction; Lic. No.: 509046-B 21427 DE LA OSA STREET      WOODLAND HILLS, CA 91364
Engineer Lu,, Ining; Lic. No.: S3042 47 E LAS FLORES AVENUE      ARCADIA, CA 91006

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/21/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 10/30/2020 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 10/30/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 10/30/2020 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 11/13/2020 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 11/13/2020 Approved OGANES TARAKHCHYAN
MERV13>=Rough 11/13/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 11/13/2020 Approved OGANES TARAKHCHYAN
Underground Mechanical 11/13/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 11/18/2020 Approved OGANES TARAKHCHYAN
Drywall Nailing 11/24/2020 Approved RICHARD ROBLES
Interior/Exterior Lathing 11/24/2020 Approved RICHARD ROBLES
ELECTRICAL-Final 7/27/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Final 7/27/2021 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 7/27/2021 Approved OGANES TARAKHCHYAN
MERV13>=Final 7/27/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 7/27/2021 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/27/2021 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 7/27/2021 Approved OGANES TARAKHCHYAN
Final 8/4/2021 Permit Finaled KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Approved KENNETH NAGLE