2450 S NALIN DR 90077
Certificate Information: 2450 S NALIN DR 90077
- Application / Permit
- 19016-20000-28282
- Plan Check / Job No.
- B19VN15149
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 6'-6" x 11'-9" PORTION OF GARAGE TO LAUNDRY ROOM; INTERIOR REMODEL
- Permit Issued
- Issued on 9/17/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/20/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2019 | SELLA BENYAMIN |
| Corrections Issued | 9/9/2019 | SELLA BENYAMIN |
| Building Plans Picked Up | 9/11/2019 | APPLICANT |
| Issued | 9/17/2019 | LADBS |
| CofO in Progress | 9/28/2020 | CARLOS MATAMOROS |
| CofO Issued | 10/20/2020 | VINCENT COTTON |
| Permit Finaled | 10/20/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/17/2019 | SELLA BENYAMIN |
Contact Information
| Contractor | B D R Inc; Lic. No.: 735996-B | P O BOX 410 AGOURA HILLS, CA 91376 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/26/2019 | Partial Approval | ANTHONY MCDOWALL |
| Underground Mechanical | 10/31/2019 | Corrections Issued | ANTHONY MCDOWALL |
| Underground Mechanical | 11/4/2019 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2019 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 11/25/2019 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 12/19/2019 | Corrections Issued | ANTHONY MCDOWALL |
| HVAC-Rough | 12/19/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Wood Frame | 12/19/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Deputy Wood Construction | 12/30/2019 | Conditional Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 12/30/2019 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2019 | Approved | ANTHONY MCDOWALL |
| Deputy Wood Construction | 12/31/2019 | Conditional Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 1/17/2020 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 1/17/2020 | Partial Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/17/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/21/2020 | Corrections Issued | CARLOS MATAMOROS |
| Insulation | 2/21/2020 | Corrections Issued | CARLOS MATAMOROS |
| Wood Frame | 2/25/2020 | Partial Approval | MATT KELLERMAN |
| Drywall Nailing | 3/10/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 3/16/2020 | Partial Approval | MATT KELLERMAN |
| Shower Pan | 3/16/2020 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 4/10/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 4/10/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 4/10/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/10/2020 | Approved | CARLOS MATAMOROS |
| Gas Test | 5/26/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 9/2/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 9/2/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 9/2/2020 | Partial Approval | CARLOS MATAMOROS |
| Smoke Detectors | 9/2/2020 | Approved | CARLOS MATAMOROS |
| Final | 9/8/2020 | Corrections Issued | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 9/8/2020 | SGSOV Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 9/11/2020 | Approved | CARLOS MATAMOROS |
| Final | 9/11/2020 | Partial Approval | CARLOS MATAMOROS |
| Green Building Final | 9/11/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 9/11/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 9/11/2020 | Approved | CARLOS MATAMOROS |
| Final | 9/28/2020 | OK to Issue CofO | CARLOS MATAMOROS |