6252 N SATSUMA AVE 91606

Certificate Information: 6252 N SATSUMA AVE 91606

Application / Permit
19016-20000-28272
Plan Check / Job No.
B19VN15139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (4'-10"x 8'-0") covered porch entry & convert (E) detached ALQ to Accessory Dwelling Unit per AB 494 and SB 229. WORK PER ENGINEER.
Permit Issued
Issued on 1/28/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 TROY DEGUZMAN
Green Plans Picked Up 10/4/2019 APPLICANT
Corrections Issued 10/10/2019 TROY DEGUZMAN
Quality Review Completed 10/15/2019 CHON CHIO KUO
Building Plans Picked Up 10/17/2019 APPLICANT
Applicant returned to address corrections 12/3/2019 TROY DEGUZMAN
Applicant returned to address corrections 1/15/2020 TROY DEGUZMAN
Plan Check Approved 1/16/2020 TROY DEGUZMAN
Issued 1/28/2020 LADBS
CofO in Progress 3/24/2021 KIM BEAUCHAMP
CofO in Progress 3/24/2021 KIM BEAUCHAMP
Permit Finaled 5/7/2021 DAVID JAMES
CofO Issued 5/7/2021 DAVID JAMES
Permit Finaled 5/7/2021 DAVID JAMES

Permit Application Clearance Information

Green Code Cleared 10/10/2019 AARON COSTA
Address approval Cleared 12/31/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 12/31/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 12/31/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/31/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/31/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 1551 RANDALL ST      GLENDALE, CA 91201

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/6/2020 Approved RAYMOND KEHOE
BUILDING-Rough-Frame 2/9/2021 Approved KIM BEAUCHAMP
Final 2/9/2021 OK to Issue CofO KIM BEAUCHAMP
Footing/Foundation/Slab 2/9/2021 Approved KIM BEAUCHAMP
Green Building Final 2/9/2021 Approved KIM BEAUCHAMP
Green Building Rough 2/9/2021 Approved KIM BEAUCHAMP
Smoke Detectors 2/9/2021 Approved KIM BEAUCHAMP
Wood Frame 2/9/2021 Approved KIM BEAUCHAMP