13677 W JUDD ST 91331

Certificate Information: 13677 W JUDD ST 91331

Application / Permit
19016-20000-27682
Plan Check / Job No.
B19VN14789
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) RECREATION ROOM TO ACCESSORY DWELLING UNIT PER SB 229 AND AB 494. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 1/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2019 APPLICANT
Assigned to Plan Check Engineer 9/3/2019 ROSENDO MEDINA
Corrections Issued 9/3/2019 ROSENDO MEDINA
Plan Check Approved 1/21/2020 ANGELICA MARTINEZ
Issued 1/21/2020 LADBS
CofO in Progress 10/22/2020 MICHEL ABAJAN
CofO Issued 2/6/2021 MICHAEL SMITH
Permit Finaled 2/6/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/3/2019 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/3/2019 GABRIEL ROBLES
Sewer availability Cleared 9/3/2019 GABRIEL ROBLES
Construction near power lines Cleared 11/3/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/24/2020 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 9/18/2020 Approved MICHEL ABAJAN
Drywall Nailing 9/18/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/18/2020 Approved MICHEL ABAJAN
Final 9/18/2020 Corrections Issued MICHEL ABAJAN
HVAC-Rough 9/18/2020 Corrections Issued MICHEL ABAJAN
METHANE-Final 9/18/2020 Approved MICHEL ABAJAN
METHANE-Rough 9/18/2020 Approved MICHEL ABAJAN
PLUMBING-Final 9/18/2020 Approved MICHEL ABAJAN
Smoke Detectors 9/18/2020 Approved MICHEL ABAJAN
Final 10/8/2020 Corrections Issued MICHEL ABAJAN
HVAC-Final 10/8/2020 Approved MICHEL ABAJAN
Final 10/22/2020 OK to Issue CofO MICHEL ABAJAN