13444 N ELDRIDGE AVE 91342
Certificate Information: 13444 N ELDRIDGE AVE 91342
- Application / Permit
- 19016-20000-27188
- Plan Check / Job No.
- B19VN14550
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 18' GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 4/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2019 | ROSENDO MEDINA |
| Corrections Issued | 8/29/2019 | ROSENDO MEDINA |
| Building Plans Picked Up | 9/25/2019 | APPLICANT |
| Applicant returned to address corrections | 3/27/2020 | ROSENDO MEDINA |
| Plan Check Approved | 4/7/2020 | ROSENDO MEDINA |
| Plan Check Approved | 4/9/2020 | ROSENDO MEDINA |
| Issued | 4/13/2020 | LADBS |
| CofO in Progress | 1/14/2021 | MISAEL ESPARZA |
| CofO Issued | 12/17/2021 | MICHAEL SMITH |
| Permit Finaled | 12/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/26/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 10/1/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/9/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/16/2020 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/16/2020 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/5/2020 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 11/5/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 11/5/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 11/5/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/17/2020 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/17/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 11/17/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/17/2020 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/19/2020 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 11/19/2020 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 11/19/2020 | Approved | MISAEL ESPARZA |
| Sewer | 11/19/2020 | Approved | MISAEL ESPARZA |
| Wood Frame | 11/19/2020 | Approved | MISAEL ESPARZA |
| Insulation | 11/24/2020 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/24/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/30/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 11/30/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 11/30/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/30/2020 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 12/9/2020 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/9/2020 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/9/2020 | Conditional Approval | MISAEL ESPARZA |
| Gas Test | 12/16/2020 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/16/2020 | Approved | MISAEL ESPARZA |
| Sewer | 12/16/2020 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/30/2020 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/8/2021 | Approved | MISAEL ESPARZA |
| Final | 1/8/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/8/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/8/2021 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 1/8/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/14/2021 | Approved | MISAEL ESPARZA |
| Final | 1/14/2021 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 1/14/2021 | Approved | MISAEL ESPARZA |
| HVAC-Final | 1/14/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 1/14/2021 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/14/2021 | SGSOV Approved | MISAEL ESPARZA |