8023-8025 N MAMMOTH AVE 91402
Certificate Information: 8023-8025 N MAMMOTH AVE 91402
- Application / Permit
- 19016-20000-26698
- Plan Check / Job No.
- B19VN14292
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 18' ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 , ALL WORK PER WFPP
- Permit Issued
- Issued on 8/26/2019
- Issuing Office
- Valley
- Current Status
- Issued on 8/26/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2019 | ALDOUS CHIC |
| Corrections Issued | 8/26/2019 | ALDOUS CHIC |
| Plan Check Approved | 8/26/2019 | RARES BODEA |
| Issued | 8/26/2019 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/26/2019 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/17/2020 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/20/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/11/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/11/2021 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/27/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/27/2021 | Approved | GREGG CUMMINGS |
| Sewer | 8/27/2021 | Approved | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 8/30/2021 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 1/31/2025 | Corrections Issued | VINCENT HANLEY |
| Wood Frame | 5/15/2025 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/22/2025 | Corrections Issued | VINCENT HANLEY |
| Pre-Inspection | 7/22/2025 | Corrections Issued | VINCENT HANLEY |
| Wood Frame | 7/22/2025 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/29/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 8/29/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/29/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 8/29/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 8/29/2025 | Approved | VINCENT HANLEY |
| Pre-Inspection | 8/29/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 8/29/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 10/9/2025 | Corrections Issued | MATTHEW NELSON |
| Insulation | 10/14/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/24/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 11/7/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 11/12/2025 | Approved | CHRISTOPHER MORFIN |
| PLUMBING-Final | 3/24/2026 | Approved | JUAN ALVARADO |