12580 1/2 W DEBELL ST 91331
Certificate Information: 12580 1/2 W DEBELL ST 91331
- Application / Permit
- 19016-20000-26384
- Plan Check / Job No.
- B19VN14122
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 17' X 18' DETACHED STORAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/2/2021
- Issuing Office
- Current Status
- CofO Issued on 3/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2019 | JENNIFER LEE |
| Corrections Issued | 9/3/2019 | JENNIFER LEE |
| Applicant returned to address corrections | 4/7/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 6/21/2021 | JENNIFER LEE |
| Plan Check Approved | 7/28/2021 | JENNIFER LEE |
| Issued | 8/2/2021 | APPLICANT |
| Building Plans Picked Up | 8/3/2021 | APPLICANT |
| CofO in Progress | 2/20/2026 | MICHEL ABAJAN |
| Permit Finaled | 3/10/2026 | RUBEN SALAS |
| CofO Issued | 3/10/2026 | RUBEN SALAS |
| Permit Finaled | 3/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/9/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 7/26/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/23/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/23/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/23/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/23/2024 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 10/3/2024 | Conditional Approval | ROBERT GOLD |
| Insulation | 10/10/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/10/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/25/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 11/4/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/19/2025 | Corrections Issued | MICHEL ABAJAN |
| Final | 5/19/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 5/19/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 5/19/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/19/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/19/2025 | Approved | MICHEL ABAJAN |
| Final | 8/5/2025 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/1/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Final | 2/19/2026 | Approved | MICHEL ABAJAN |
| Final | 2/19/2026 | OK to Issue CofO | MICHEL ABAJAN |