6235 N FARMDALE AVE 91606
Certificate Information: 6235 N FARMDALE AVE 91606
- Application / Permit
- 19016-20000-26355
- Plan Check / Job No.
- B19VN14102
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) IRREGULAR 36' X 40' DETACHED RECREATION ROOM TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/31/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | JENNIFER LEE |
| Corrections Issued | 8/29/2019 | JENNIFER LEE |
| Plan Check Approved | 12/31/2019 | HERNAN ARREOLA |
| Issued | 12/31/2019 | LADBS |
| CofO in Progress | 11/16/2020 | DANIEL DREW |
| CofO Issued | 1/9/2021 | MICHAEL SMITH |
| Permit Finaled | 1/9/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/4/2019 | RIDWAN HARDY |
| Address approval | Cleared | 12/31/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/31/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/11/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/27/2020 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 10/27/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/27/2020 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 10/27/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 10/27/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/27/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/27/2020 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 10/27/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/16/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 11/16/2020 | Approved | DANIEL DREW |
| Final | 11/16/2020 | OK to Issue CofO | DANIEL DREW |
| Footing/Foundation/Slab | 11/16/2020 | Approved | DANIEL DREW |
| Green Building Final | 11/16/2020 | Approved | DANIEL DREW |
| Green Building Rough | 11/16/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 11/16/2020 | Approved | DANIEL DREW |