14015 W HAMLIN ST 91401

Certificate Information: 14015 W HAMLIN ST 91401

Application / Permit
19016-20000-26321
Plan Check / Job No.
B19VN14084
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Remove existing 11' x 20' attached storage and convert remaining 18' x 20' detached garage into an Accessory Dwelling Unit per AB 494 & SB 229. All work per WFPP.
Permit Issued
Issued on 9/25/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 ANGELICA DAVE
Corrections Issued 8/22/2019 ANGELICA DAVE
Plan Check Approved 8/23/2019 RAPHAEL ROSAS
Issued 9/25/2019 LADBS
CofO in Progress 7/29/2020 WILLIAM KUEHN
No Progress 11/7/2020 MICHAEL TEMPLE
CofO in Progress 1/25/2021 MICHAEL TEMPLE
CofO Issued 2/9/2021 MICHAEL SMITH
Permit Finaled 2/9/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/22/2019 GUILLERMO PETRA
Construction near power lines Cleared 8/22/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 8/22/2019 GUILLERMO PETRA
Permit Cleared 8/22/2019 GUILLERMO PETRA
Sewer availability Cleared 8/22/2019 GUILLERMO PETRA
Trees in Parkway Cleared 8/22/2019 JOHN KIM

Contact Information

Contractor 52 Star Construction Inc; Lic. No.: 1042404-B 30525 CANWOOD ST      AGOURA HILLS, CA 91301

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/24/2019 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 12/6/2019 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 12/10/2019 Corrections Issued ROBERT MINASSIANS
Underground Mechanical 12/10/2019 Corrections Issued ROBERT MINASSIANS
Sewer 12/12/2019 Approved ARAM AVEDISIAN
Underground Mechanical 12/12/2019 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 12/13/2019 Approved ARAM AVEDISIAN
PLUMBING-Rough 12/16/2019 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 12/20/2019 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 12/20/2019 Not Ready for Inspection PIERRE VEGA
Green Building Rough 12/20/2019 Not Ready for Inspection PIERRE VEGA
Interior/Exterior Lathing 12/20/2019 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 12/20/2019 Not Ready for Inspection PIERRE VEGA
BUILDING-Rough-Frame 12/24/2019 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 12/24/2019 Approved ARAM AVEDISIAN
Green Building Rough 12/24/2019 Approved ARAM AVEDISIAN
PLUMBING-Rough 12/24/2019 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 1/6/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 1/6/2020 Partial Approval JENNIFER RABUCHIN
Insulation 1/6/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 1/10/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/10/2020 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 1/15/2020 Approved ARAM AVEDISIAN
Shower Pan 1/15/2020 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Approved MISAEL ESPARZA
Final 3/31/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 3/31/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/31/2020 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 3/31/2020 Approved MISAEL ESPARZA
Pre-Inspection 4/15/2020 Approved MISAEL ESPARZA
Pre-Inspection 5/11/2020 Approved MISAEL ESPARZA
Final 6/11/2020 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/11/2020 SGSOV Not Ready THOMAS FINNILA
Sewer 7/10/2020 Partial Inspection MISAEL ESPARZA
Final 7/28/2020 OK to Issue CofO WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 7/28/2020 SGSOV Approved WILLIAM KUEHN
Special/Order Compliance 11/9/2020 Corrections Issued WILLIAM KUEHN
Pre-Inspection 1/25/2021 Approved MICHAEL TEMPLE