12754 W WEDDINGTON ST 91607
Certificate Information: 12754 W WEDDINGTON ST 91607
- Application / Permit
- 19016-20000-25052
- Plan Check / Job No.
- B19VN13435
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 6/19/2020
- Issuing Office
- Current Status
- CofO Issued on 12/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2019 | JEFFREY TANGONAN |
| Corrections Issued | 8/13/2019 | JEFFREY TANGONAN |
| Building Plans Picked Up | 8/15/2019 | APPLICANT |
| Plan Check Approved | 8/23/2019 | JEROME MAGAT PALMA |
| Issued | 6/19/2020 | APPLICANT |
| CofO in Progress | 10/23/2020 | BRENDAN LOONEY |
| CofO Issued | 12/25/2021 | MICHAEL SMITH |
| Permit Finaled | 12/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 8/15/2019 | APEKSHYA BAJRACHARYA |
| Specific Plan | Cleared | 8/23/2019 | DANIEL SKOLNICK |
Contact Information
| Contractor | G & F Construction Inc; Lic. No.: 930879-B | 13151 SHERMAN WAY UNIT B NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2020 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 6/25/2020 | Partial Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 7/6/2020 | Conditional Approval | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 7/20/2020 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 7/20/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 7/20/2020 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 7/20/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/20/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/28/2020 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 7/28/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 7/28/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 7/28/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 7/28/2020 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/3/2020 | Approved | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 8/3/2020 | Conditional Approval | DANIEL ORRANTE |
| ELECTRICAL-Rough | 8/3/2020 | Approved | BRENDAN LOONEY |
| Green Building Rough | 8/3/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 8/3/2020 | Approved | BRENDAN LOONEY |
| Insulation | 8/6/2020 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/6/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 8/11/2020 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/14/2020 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/21/2020 | Approved | BRENDAN LOONEY |
| Green Building Final | 10/1/2020 | Conditional Approval | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 10/1/2020 | SGSOV Not Required | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 10/9/2020 | Approved | BRENDAN LOONEY |
| Final | 10/9/2020 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 10/9/2020 | Approved | BRENDAN LOONEY |
| Green Building Rough | 10/9/2020 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 10/9/2020 | Corrections Issued | BRENDAN LOONEY |
| Final | 10/22/2020 | OK to Issue CofO | BRENDAN LOONEY |
| Smoke Detectors | 10/22/2020 | Approved | BRENDAN LOONEY |