9419 N FARRALONE AVE 91311
Certificate Information: 9419 N FARRALONE AVE 91311
- Application / Permit
- 19016-20000-24607
- Plan Check / Job No.
- B19VN13226
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 15'-9" X 20'-5" PORTION OF (E) 3-CAR GARAGE TO (N) BEDROOM/BATHROOM, REMOVE (E) INTERIOR WALL BETWEEN DINING/LIVING ROOM AND REPLACE WITH NEW BEAM, REMOVE AND REPLACE (E) WINDOWS/DOORS. ALL WORK PER ENGINEERING."COMPLY WITH DEPARTMENT ORDER effective date 10/19/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 12/16/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/22/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2019 | JENNIFER LEE |
| Corrections Issued | 8/7/2019 | JENNIFER LEE |
| Applicant returned to address corrections | 11/4/2019 | TROY DEGUZMAN |
| Plan Check Approved | 11/26/2019 | JEROME MAGAT PALMA |
| Issued | 12/16/2019 | LADBS |
| CofO in Progress | 9/4/2020 | HAGOP BADOSSIAN |
| CofO Issued | 12/22/2020 | DAVID JAMES |
| Permit Finaled | 12/22/2020 | DAVID JAMES |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/26/2019 | BRIAN MILLER |
| Specific Plan | Cleared | 9/26/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 9/26/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 9/26/2019 | HERMINIGILDO AGUSTIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/18/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbander,, Mohamad Nabil; Lic. No.: C61250 | 205 SAINT VINCENT IRVINE, CA 92618 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/21/2020 | Approved | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 1/24/2020 | Approved | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 2/18/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 2/20/2020 | Approved | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 2/24/2020 | Partial Approval | HAGOP BADOSSIAN |
| Wood Frame | 3/23/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 3/24/2020 | Conditional Approval | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 4/1/2020 | Partial Approval | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 4/6/2020 | Partial Approval | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 5/6/2020 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Rough | 5/6/2020 | Corrections Issued | HAGOP BADOSSIAN |
| Insulation | 5/8/2020 | Approved | MARK DOVICO |
| PLUMBING-Rough | 5/8/2020 | Approved | MARK DOVICO |
| Drywall Nailing | 5/13/2020 | Conditional Approval | HAGOP BADOSSIAN |
| Shower Pan | 5/18/2020 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 5/20/2020 | Approved | HAGOP BADOSSIAN |
| Drywall Nailing | 7/14/2020 | Approved | HAGOP BADOSSIAN |
| Final | 7/14/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Smoke Detectors | 7/14/2020 | Approved | HAGOP BADOSSIAN |
| Final | 9/3/2020 | Conditional Approval | HAGOP BADOSSIAN |