435-435 1/2 E 21ST ST 90011
Certificate Information: 435-435 1/2 E 21ST ST 90011
- Application / Permit
- 19016-20000-24238
- Plan Check / Job No.
- B19VN13059
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 21' X 22' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP. "COMPLY WITH DEPARMENT ORDER EFFECTIVE DATE 8/8/19. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 11/26/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/30/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2019 | JENNIFER LEE |
| Corrections Issued | 8/14/2019 | JENNIFER LEE |
| Plan Check Approved | 11/14/2019 | ANGELICA MARTINEZ |
| Issued | 11/26/2019 | LADBS |
| CofO in Progress | 11/30/2020 | MARIO CUEVAS |
| Permit Finaled | 11/30/2020 | BRUCE TODD |
| CofO Issued | 11/30/2020 | BRUCE TODD |
| Permit Finaled | 11/30/2020 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 8/14/2019 | APEKSHYA BAJRACHARYA |
| ZI | Cleared | 8/27/2019 | STEVE GARCIA |
| Construction near power lines | Cleared | 11/14/2019 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/12/2019 | No Access for Inspection | MARIO CUEVAS |
| Pre-Inspection | 12/13/2019 | Approved | MARIO CUEVAS |
| Footing/Foundation/Slab | 1/16/2020 | Corrections Issued | MARIO CUEVAS |
| Pre-Inspection | 1/16/2020 | Not Ready for Inspection | MARIO CUEVAS |
| BUILDING-Rough-Frame | 2/25/2020 | Not Ready for Inspection | MARIO CUEVAS |
| Footing/Foundation/Slab | 2/25/2020 | Approved | MARIO CUEVAS |
| Green Building Rough | 2/25/2020 | Not Ready for Inspection | MARIO CUEVAS |
| ELECTRICAL-Rough | 3/5/2020 | Not Ready for Inspection | MARIO CUEVAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Approved | MARIO CUEVAS |
| Wood Frame | 3/5/2020 | Not Ready for Inspection | MARIO CUEVAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Approved | MARIO CUEVAS |
| Rough-Elec/Plmb/HVAC | 3/20/2020 | Corrections Issued | MARIO CUEVAS |
| Insulation | 3/26/2020 | Approved | MARIO CUEVAS |
| Rough-Elec/Plmb/HVAC | 3/26/2020 | Approved | MARIO CUEVAS |
| Wood Frame | 3/26/2020 | Approved | MARIO CUEVAS |
| Drywall Nailing | 4/7/2020 | Not Ready for Inspection | MARIO CUEVAS |
| Green Building Rough | 4/7/2020 | Approved | MARIO CUEVAS |
| Sewer | 4/23/2020 | Approved | MARIO CUEVAS |
| BUILDING-Rough-Frame | 4/24/2020 | Approved | MARIO CUEVAS |
| Drywall Nailing | 4/24/2020 | Approved | MARIO CUEVAS |
| Interior/Exterior Lathing | 4/24/2020 | Approved | MARIO CUEVAS |
| Final | 7/9/2020 | Corrections Issued | MARIO CUEVAS |
| Green Building Final | 7/9/2020 | Not Ready for Inspection | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 7/9/2020 | SGSOV Not Ready | MARIO CUEVAS |
| Smoke Detectors | 7/9/2020 | Not Ready for Inspection | MARIO CUEVAS |
| Final | 8/25/2020 | Corrections Issued | MARIO CUEVAS |
| Gas Test | 8/25/2020 | Corrections Issued | MARIO CUEVAS |
| Green Building Final | 8/25/2020 | Approved | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 8/25/2020 | SGSOV Not Ready | MARIO CUEVAS |
| Smoke Detectors | 8/25/2020 | Approved | MARIO CUEVAS |
| Final | 9/16/2020 | Not Ready for Inspection | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 9/16/2020 | SGSOV Approved | MARIO CUEVAS |
| Final | 9/25/2020 | Conditional Approval | MARIO CUEVAS |