9160 N RESEDA BLVD 91324

Certificate Information: 9160 N RESEDA BLVD 91324

Application / Permit
19016-20000-24061
Plan Check / Job No.
B19VN12953
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant - Drive Through Fast Food
Work Description
ARCHITECTURAL & STRUCTURAL ALTERATIONS OF EXISTING RESTAUARANT. ADD ROOF SUPPORT FOR HVAC EQUIPMENT. ADD CANOPY OVER DRIVE-THROUGH WINDOW
Permit Issued
Issued on 3/6/2020
Issuing Office
Metro
Current Status
Permit Finaled on 6/25/2020

Permit Application Status History

Submitted 8/2/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 RUDOLF KINAR MELIKOFF
Corrections Issued 8/26/2019 RUDOLF KINAR MELIKOFF
Quality Review Completed 8/30/2019 STEVEN KIM
Building Plans Picked Up 9/3/2019 APPLICANT
Disabled Access Plans Picked Up 9/3/2019 APPLICANT
Green Plans Picked Up 9/3/2019 APPLICANT
Applicant returned to address corrections 12/20/2019 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 12/23/2019 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 2/7/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 2/14/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 2/21/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 2/28/2020 RUDOLF KINAR MELIKOFF
Plan Check Approved 3/2/2020 RUDOLF KINAR MELIKOFF
Issued 3/6/2020 LADBS
Permit Finaled 6/25/2020 JEFFREY FULTON

Permit Application Clearance Information

ZA Case Cleared 9/17/2019 HERMINIGILDO AGUSTIN
ZA Case Cleared 9/17/2019 HERMINIGILDO AGUSTIN
ZA Case Cleared 9/17/2019 HERMINIGILDO AGUSTIN
"Q" conditions Cleared 12/6/2019 TERRI OSBORNE
CPC Cleared 12/6/2019 TERRI OSBORNE
ZA Case Cleared 12/6/2019 TERRI OSBORNE
Address approval Cleared 12/19/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/19/2019 ADRIAN CASTRO
Green Code Cleared 12/19/2019 DAVID MATSON
Sewer availability Cleared 12/19/2019 ADRIAN CASTRO
Hydrant and Access approval Cleared 12/20/2019 GEORGE SUCHAND
Prkng lot landscape/Water mgmt Cleared 1/8/2020 HERMINIGILDO AGUSTIN
Low Impact Development Cleared 1/17/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/17/2020 THOMAS LANG
Drive-through fast food Cleared 2/7/2020 STEVEN WECHSLER
Food establishment approval Cleared 2/7/2020 LACDHS APPROVED
Food Service Establishment Cleared 2/12/2020 KENNETH BROWNE
Comm Cor/Mini-Mall Cleared 2/14/2020 VINCENT QUITORIANO
DAS Clearance Cleared 3/2/2020 RUDOLF KINAR MELIKOFF

Contact Information

Architect Dungan,, John M; Lic. No.: C32116 8826 SANTA FE DRIVE SUITE 304      OVERLAND PARK, KS 66212
Contractor Cirks Construction Inc; Lic. No.: 763589-B 1442 E LINCOLN AVENUE #334      ORANGE, CA 92865
Engineer Sommer,, Rodney Wayne; Lic. No.: C47871 17411 NE 130TH PO BOX 1032      KEARNEY, MO 640601032

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/27/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 3/31/2020 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/31/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 4/7/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 4/10/2020 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 4/10/2020 No Access for Inspection JEFFREY FULTON
Footing/Foundation/Slab 4/13/2020 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 4/16/2020 Partial Inspection JEFFREY FULTON
Wood Frame 4/17/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 No Access for Inspection JEFFREY FULTON
Structural Steel Frame 4/21/2020 No Access for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval JONATHAN QUACH
Structural Steel Frame 4/22/2020 Approved JONATHAN QUACH
Wood Frame 4/22/2020 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 4/24/2020 Conditional Approval JEFFREY FULTON
Drywall Nailing 4/24/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Partial Inspection JEFFREY FULTON
Insulation 4/24/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 4/27/2020 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 4/29/2020 Partial Inspection JEFFREY FULTON
Wood Frame 4/29/2020 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 5/4/2020 Approved JEFFREY FULTON
T-Bar Ceiling 5/6/2020 Partial Inspection JEFFREY FULTON
Special/Order Compliance 5/28/2020 Corrections Issued JEFFREY FULTON
Final 6/15/2020 Not Ready for Inspection JEFFREY FULTON
Green Building Final 6/15/2020 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 6/15/2020 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 6/15/2020 Not Ready for Inspection JEFFREY FULTON
Final 6/19/2020 Not Ready for Inspection JEFFREY FULTON
Green Building Final 6/19/2020 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 6/19/2020 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 6/19/2020 Approved JEFFREY FULTON
Final 6/25/2020 Permit Finaled JEFFREY FULTON
Green Building Final 6/25/2020 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 6/25/2020 SGSOV Approved JEFFREY FULTON