3468 N DIVISION ST 90065

Certificate Information: 3468 N DIVISION ST 90065

Application / Permit
19016-20000-24002
Plan Check / Job No.
B19VN12908
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 18' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORKS ARE PER DESIGN
Permit Issued
Issued on 10/8/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2019 APPLICANT
Assigned to Plan Check Engineer 8/2/2019 ALDOUS CHIC
Corrections Issued 8/2/2019 ALDOUS CHIC
Plan Check Approved 10/4/2019 PINANK PATEL
Issued 10/8/2019 LADBS
CofO in Progress 7/17/2020 OSVALDO PARAMO
CofO in Progress 7/17/2020 OSVALDO PARAMO
CofO in Progress 7/17/2020 OSVALDO PARAMO
Permit Finaled 9/23/2020 DEROLD HAUFF
CofO Issued 9/23/2020 DEROLD HAUFF
Permit Finaled 9/23/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/2/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/2/2019 GUILLERMO PETRA
Grading Pre-Inspection Cleared 8/2/2019 ALDOUS CHIC
Sewer availability Cleared 8/2/2019 GUILLERMO PETRA
Specific Plan Cleared 10/3/2019 OLGA RUANO
ZI Cleared 10/4/2019 NICOLE SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Oyen,, Paul Erling; Lic. No.: S5730 1977 NOLDEN ST      LOS ANGELES, CA 90041

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/11/2019 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 11/14/2019 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 11/14/2019 Approved OSVALDO PARAMO
Footing/Foundation/Slab 11/25/2019 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/2/2019 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/5/2019 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 12/19/2019 Partial Approval BRIAN SULLIVAN
HVAC-Rough 12/19/2019 Approved BRIAN SULLIVAN
PLUMBING-Rough 12/19/2019 Partial Approval BRIAN SULLIVAN
Wood Frame 12/19/2019 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 12/23/2019 Approved RUBEN SALAS
HVAC-Rough 12/23/2019 Approved RUBEN SALAS
PLUMBING-Rough 12/23/2019 Approved RUBEN SALAS
Insulation 12/27/2019 Approved OSVALDO PARAMO
Wood Frame 12/30/2019 Approved OSVALDO PARAMO
Drywall Nailing 1/6/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 1/6/2020 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 1/8/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 2/13/2020 Approved OSVALDO PARAMO
Final 2/13/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 2/13/2020 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 2/13/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/13/2020 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 2/13/2020 Approved OSVALDO PARAMO
Final 2/27/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 2/27/2020 Approved OSVALDO PARAMO
Final 3/5/2020 OK to Issue CofO OSVALDO PARAMO