4562 E JADE ST 90032

Certificate Information: 4562 E JADE ST 90032

Application / Permit
19016-20000-23902
Plan Check / Job No.
B19VN12867
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTDETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB494 AND SB229. ALL WORKS ARE PER DESIGN
Permit Issued
Issued on 1/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2019 APPLICANT
Assigned to Plan Check Engineer 8/2/2019 ALDOUS CHIC
Corrections Issued 8/5/2019 ALDOUS CHIC
Building Plans Picked Up 8/5/2019 APPLICANT
Plan Check Approved 12/3/2019 ALDOUS CHIC
Issued 1/9/2020 LADBS
CofO in Progress 7/13/2020 ENRIQUE MIRELES
Permit Finaled 7/31/2020 DEROLD HAUFF
CofO Issued 7/31/2020 DEROLD HAUFF
Permit Finaled 7/31/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/12/2019 GABRIEL ROBLES
Construction near power lines Cleared 8/12/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 8/12/2019 GABRIEL ROBLES
Miscellaneous Cleared 8/12/2019 GABRIEL ROBLES
Sewer availability Cleared 8/12/2019 GABRIEL ROBLES
Grading Pre-Inspection Cleared 11/22/2019 MANUEL TEJADA
"D" conditions Cleared 11/26/2019 ANNA VAN
"Q" conditions Cleared 11/26/2019 ANNA VAN
ZI Cleared 11/26/2019 ANNA VAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor L E A D Enterprises Inc; Lic. No.: 955824-B 6803 YARMOUTH AVENUE      RESEDA, CA 91335

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2020 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 2/26/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/26/2020 Approved ENRIQUE MIRELES
Wood Frame 2/26/2020 Not Ready for Inspection ENRIQUE MIRELES
Insulation 3/2/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/2/2020 Partial Approval ENRIQUE MIRELES
BUILDING-Rough-Frame 3/4/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/4/2020 Approved ENRIQUE MIRELES
Green Building Rough 3/4/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/20/2020 Approved ENRIQUE MIRELES
Shower Pan 3/20/2020 Approved ENRIQUE MIRELES
Drywall Nailing 3/26/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/26/2020 Approved ENRIQUE MIRELES
Final 6/11/2020 Corrections Issued ENRIQUE MIRELES
Green Building Final 6/11/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/11/2020 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 6/11/2020 Approved ENRIQUE MIRELES
Final 6/22/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 6/25/2020 Corrections Issued ENRIQUE MIRELES
Final 7/13/2020 OK to Issue CofO ENRIQUE MIRELES