14228 W RAVEN ST 91342
Certificate Information: 14228 W RAVEN ST 91342
- Application / Permit
- 19016-20000-23833
- Plan Check / Job No.
- B19VN12824
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229; REMOVE 10' X 12' BREEZEWAY TO DETACH GARAGE FROM DWELLING
- Permit Issued
- Issued on 10/16/2020
- Issuing Office
- Current Status
- CofO Issued on 5/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | ALDOUS CHIC |
| Corrections Issued | 8/1/2019 | ALDOUS CHIC |
| Plan Check Approved | 8/12/2019 | SELLA BENYAMIN |
| Issued | 10/16/2020 | APPLICANT |
| CofO in Progress | 3/9/2021 | MISAEL ESPARZA |
| CofO Issued | 5/1/2021 | MICHAEL SMITH |
| Permit Finaled | 5/1/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2019 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2019 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/1/2019 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/20/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 11/20/2020 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/2/2020 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/17/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/17/2020 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 12/17/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/17/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/24/2020 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 12/24/2020 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/29/2020 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 12/29/2020 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 12/29/2020 | Approved | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 12/29/2020 | Approved | MISAEL ESPARZA |
| Insulation | 12/30/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 1/4/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/4/2021 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 1/4/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/5/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/11/2021 | Approved | MISAEL ESPARZA |
| Final | 2/11/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/11/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 2/11/2021 | Approved | MISAEL ESPARZA |
| Final | 2/22/2021 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Final | 2/22/2021 | No Access for Inspection | MISAEL ESPARZA |
| Final | 2/26/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 2/26/2021 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 3/1/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 3/9/2021 | Approved | MISAEL ESPARZA |
| Final | 3/9/2021 | OK to Issue CofO | MISAEL ESPARZA |
| HVAC-Final | 3/9/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 3/9/2021 | Approved | MISAEL ESPARZA |