7244 N CAMELLIA AVE 91605
Certificate Information: 7244 N CAMELLIA AVE 91605
- Application / Permit
- 19016-20000-23679
- Plan Check / Job No.
- B19VN12727
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE/RECREATION ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2019 | ALDOUS CHIC |
| Corrections Issued | 7/31/2019 | ALDOUS CHIC |
| Plan Check Approved | 1/29/2020 | ALDOUS CHIC |
| Issued | 1/29/2020 | LADBS |
| CofO in Progress | 5/25/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
| CofO Issued | 6/8/2023 | MICHAEL SMITH |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/31/2019 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 11/4/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/15/2021 | No Result Entered | RAYMOND KEHOE |
| Footing/Foundation/Slab | 10/19/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 11/24/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/24/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 11/24/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/24/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 11/24/2021 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 11/24/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/22/2022 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 2/22/2022 | Approved | CALEB MEISTER |
| Green Building Rough | 2/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 2/22/2022 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 2/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 2/22/2022 | Not Ready for Inspection | CALEB MEISTER |
| Pre-Inspection | 2/28/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/7/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 3/7/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 3/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/24/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 3/24/2022 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 3/24/2022 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 3/24/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/5/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 5/5/2022 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 5/5/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 5/27/2022 | Approved | CALEB MEISTER |
| Insulation | 5/27/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 5/27/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 6/6/2022 | Approved | MISAEL ESPARZA |
| Final | 5/12/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 5/12/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/12/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 5/12/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| Final | 5/24/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/24/2023 | Approved | JENNIFER RABUCHIN |