2817 S RIMPAU BLVD 90016

Certificate Information: 2817 S RIMPAU BLVD 90016

Application / Permit
19016-20000-23211
Plan Check / Job No.
B19VN12525
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 25' X 38' IRREGULAR DETACHED GARAGE/ RECREATION ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 1/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2019 APPLICANT
Assigned to Plan Check Engineer 7/29/2019 ROSENDO MEDINA
Corrections Issued 7/30/2019 ROSENDO MEDINA
Building Plans Picked Up 8/16/2019 APPLICANT
Applicant returned to address corrections 11/22/2019 ROSENDO MEDINA
Plan Check Approved 1/17/2020 ROSENDO MEDINA
Issued 1/17/2020 LADBS
CofO in Progress 9/30/2020 STUART CHAPMAN
Permit Finaled 10/8/2020 DEROLD HAUFF
CofO Issued 10/8/2020 DEROLD HAUFF
Permit Finaled 10/8/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/23/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/23/2019 GUILLERMO PETRA
Sewer availability Cleared 8/23/2019 GUILLERMO PETRA
Construction near power lines Cleared 1/15/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/24/2020 Approved CHARLENE BUSTAMANTE
Footing/Foundation/Slab 2/24/2020 Approved CHARLENE BUSTAMANTE
PLUMBING-Rough 2/24/2020 Conditional Approval CHARLENE BUSTAMANTE
Drywall Nailing 2/28/2020 Partial Inspection CHARLES BOGHOSKHAN
Green Building Rough 2/28/2020 Partial Inspection CHARLES BOGHOSKHAN
BUILDING-Rough-Frame 3/4/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 3/4/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Insulation 3/4/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/24/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 3/24/2020 Approved KATHRYN BUTTERWORTH
Insulation 3/24/2020 Approved KATHRYN BUTTERWORTH
Drywall Nailing 3/31/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 3/31/2020 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 4/7/2020 Partial Approval SABAS ALONSO
HVAC-Final 6/2/2020 Approved STUART CHAPMAN
ELECTRICAL-Final 7/1/2020 Approved STUART CHAPMAN
Final 7/1/2020 Conditional Approval STUART CHAPMAN
Green Building Final 7/1/2020 Approved STUART CHAPMAN
HVAC-Final 7/1/2020 Approved STUART CHAPMAN
PLUMBING-Final 7/1/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/1/2020 SGSOV Approved STUART CHAPMAN
Smoke Detectors 7/1/2020 Approved STUART CHAPMAN