2817 S RIMPAU BLVD 90016
Certificate Information: 2817 S RIMPAU BLVD 90016
- Application / Permit
- 19016-20000-23211
- Plan Check / Job No.
- B19VN12525
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 25' X 38' IRREGULAR DETACHED GARAGE/ RECREATION ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2019 | ROSENDO MEDINA |
| Corrections Issued | 7/30/2019 | ROSENDO MEDINA |
| Building Plans Picked Up | 8/16/2019 | APPLICANT |
| Applicant returned to address corrections | 11/22/2019 | ROSENDO MEDINA |
| Plan Check Approved | 1/17/2020 | ROSENDO MEDINA |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 9/30/2020 | STUART CHAPMAN |
| Permit Finaled | 10/8/2020 | DEROLD HAUFF |
| CofO Issued | 10/8/2020 | DEROLD HAUFF |
| Permit Finaled | 10/8/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/23/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 1/15/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/24/2020 | Approved | CHARLENE BUSTAMANTE |
| Footing/Foundation/Slab | 2/24/2020 | Approved | CHARLENE BUSTAMANTE |
| PLUMBING-Rough | 2/24/2020 | Conditional Approval | CHARLENE BUSTAMANTE |
| Drywall Nailing | 2/28/2020 | Partial Inspection | CHARLES BOGHOSKHAN |
| Green Building Rough | 2/28/2020 | Partial Inspection | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 3/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 3/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 3/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/24/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 3/24/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 3/24/2020 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 3/31/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 3/31/2020 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 4/7/2020 | Partial Approval | SABAS ALONSO |
| HVAC-Final | 6/2/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 7/1/2020 | Approved | STUART CHAPMAN |
| Final | 7/1/2020 | Conditional Approval | STUART CHAPMAN |
| Green Building Final | 7/1/2020 | Approved | STUART CHAPMAN |
| HVAC-Final | 7/1/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 7/1/2020 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2020 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 7/1/2020 | Approved | STUART CHAPMAN |