10164-10166 N CASABA AVE 91311

Certificate Information: 10164-10166 N CASABA AVE 91311

Application / Permit
19016-20000-23112
Plan Check / Job No.
B19VN12469
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 7/29/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2019 APPLICANT
Assigned to Plan Check Engineer 7/26/2019 ALDOUS CHIC
Corrections Issued 7/26/2019 ALDOUS CHIC
Plan Check Approved 7/29/2019 ARTIN ZARUKIAN
Issued 7/29/2019 LADBS
CofO in Progress 4/22/2020 VINCENT HANLEY
Permit Finaled 6/16/2020 DONALD SUNSERI
CofO Issued 6/16/2020 DONALD SUNSERI
Permit Finaled 6/16/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 7/26/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 7/26/2019 JOHN LIN
Sewer availability Cleared 7/26/2019 JOHN LIN

Contact Information

No Data Available.

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/14/2019 Approved VINCENT HANLEY
Sewer 8/14/2019 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/4/2019 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 9/4/2019 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 9/24/2019 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 9/24/2019 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 10/9/2019 Approved VINCENT HANLEY
ELECTRICAL-Rough 10/9/2019 Approved VINCENT HANLEY
Green Building Rough 10/9/2019 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 10/9/2019 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/16/2019 Approved VINCENT HANLEY
Insulation 10/16/2019 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/16/2019 Partial Approval VINCENT HANLEY
Rough-Elec/Plmb/HVAC 10/16/2019 Approved VINCENT HANLEY
Drywall Nailing 10/24/2019 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/24/2019 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/18/2019 Approved PETER FOLLING
Service/Power Release 3/2/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/10/2020 Approved DAVID SANDOVAL
Final 3/10/2020 Corrections Issued DAVID SANDOVAL
Green Building Final 3/10/2020 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 3/10/2020 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/10/2020 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 3/10/2020 Not Ready for Inspection DAVID SANDOVAL
Final 3/19/2020 Not Ready for Inspection DONALD SUNSERI
Green Building Final 3/19/2020 Approved DONALD SUNSERI
SGSOV-Seismic Gas S/O Valve 3/19/2020 SGSOV Gas Company DONALD SUNSERI
Smoke Detectors 3/19/2020 Approved DONALD SUNSERI
Final 3/25/2020 Corrections Issued DONALD SUNSERI
ELECTRICAL-Final 4/21/2020 Approved VINCENT HANLEY
Final 4/21/2020 OK to Issue CofO VINCENT HANLEY
HVAC-Final 4/21/2020 Approved VINCENT HANLEY
PLUMBING-Final 4/21/2020 Approved VINCENT HANLEY
Service/Power Release 4/21/2020 Approved VINCENT HANLEY