1818 W 71ST ST 90047
Certificate Information: 1818 W 71ST ST 90047
- Application / Permit
- 19016-20000-23092
- Plan Check / Job No.
- B19VN12458
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Non structural interior/exterior renovaion: re-roof, resurface & restripe parking, install stairs railing, renovate 4 units for accessibility, replace entry ramp/siding/doors/windows/flooring and repair corridor. All per design. See comment
- Permit Issued
- Issued on 12/13/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2019 | APPLICANT |
| Green Plans Picked Up | 8/13/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 8/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2019 | ALDOUS CHIC |
| Corrections Issued | 8/26/2019 | ALDOUS CHIC |
| Quality Review Completed | 8/27/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 8/30/2019 | APPLICANT |
| Applicant returned to address corrections | 10/17/2019 | ALDOUS CHIC |
| Plan Check Approved | 12/13/2019 | ALDOUS CHIC |
| Issued | 12/13/2019 | LADBS |
| CofO in Progress | 4/13/2021 | LANNY MERRICK |
| CofO Issued | 4/13/2021 | ERNESTO CORRAL |
| Permit Finaled | 4/13/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/27/2019 | MICHAEL GREGERSON |
| Community Plan Implem. Overlay | Cleared | 9/4/2019 | OSCAR CASTRO |
| ZI | Cleared | 9/4/2019 | ANNA VIDAL |
| Project located in CRA area | Cleared | 9/10/2019 | JIM URQUHART |
| Community Plan Implem. Overlay | Cleared | 9/11/2019 | ERIK BEASLEY |
| Community Plan Implem. Overlay | Cleared | 9/24/2019 | JOHN KIM |
| "D" conditions | Cleared | 10/8/2019 | RINA LARA |
| Frnt yard landscape/Water mgmt | Cleared | 10/8/2019 | RINA LARA |
| Opn space landscape/Water mgmt | Cleared | 10/8/2019 | RINA LARA |
| Prkng lot landscape/Water mgmt | Cleared | 10/8/2019 | RINA LARA |
| Green Code | Cleared | 10/10/2019 | MICHAEL AYERS |
| Low Impact Development | Cleared | 10/10/2019 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/13/2019 | ADRIAN CASTRO |
| Fire Marshall Fire Life Safety | Cleared | 11/15/2019 | WILLIAM JOHNS |
| ZI | Cleared | 11/21/2019 | HELEN JADALI |
| ZI | Cleared | 11/21/2019 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 12/13/2019 | EDUARDO HERMOSO |
| DAS Clearance | Cleared | 12/13/2019 | NORLITO MEDRANO |
| Public Housing | Cleared | 12/13/2019 | GUS VINDELL |
Contact Information
| Architect | Brookie,, Dean Robert; Lic. No.: C20516 | 970 E 4TH AVENUE DURANGO, CO 81301 |
| Contractor | Mfrg-Icon Construction; Lic. No.: 1031179-B | 2461 SANTA MONICA BLVD STE 150 SANTA MONICA, CA 90404 |
| Contractor | Owner-Builder | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 3/4/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 3/4/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Green Building Rough | 3/27/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 3/27/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 4/1/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 4/14/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 4/22/2020 | Approved | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 5/6/2020 | Approved | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 5/6/2020 | Approved | LEOPOLDO MENDOZA |
| Pre-Inspection | 6/19/2020 | Corrections Issued | LEOPOLDO MENDOZA |
| Green Building Rough | 6/26/2020 | Approved | LEOPOLDO MENDOZA |
| Wood Frame | 6/26/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Insulation | 6/30/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 7/2/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 7/8/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Pre-Inspection | 7/10/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Wood Frame | 7/30/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 8/3/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Final | 8/21/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 8/21/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Not Ready | LEOPOLDO MENDOZA |
| Smoke Detectors | 8/21/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 8/21/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 8/25/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 8/28/2020 | Corrections Issued | LEOPOLDO MENDOZA |
| Drywall Nailing | 9/11/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 9/11/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 9/17/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Wood Frame | 9/29/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Pre-Inspection | 10/14/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Pre-Inspection | 10/15/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Pre-Inspection | 10/16/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Pre-Inspection | 10/19/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 11/13/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 11/19/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Drywall Nailing | 12/3/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Insulation | 12/3/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Wood Frame | 12/3/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Final | 2/24/2021 | Not Ready for Inspection | LANNY MERRICK |
| Green Building Final | 2/24/2021 | Approved | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 2/24/2021 | SGSOV Approved | LANNY MERRICK |
| Smoke Detectors | 2/24/2021 | Not Ready for Inspection | LANNY MERRICK |
| Wood Frame | 2/24/2021 | Approved | LANNY MERRICK |
| Final | 3/1/2021 | Partial Inspection | LANNY MERRICK |
| Smoke Detectors | 3/1/2021 | Approved | LANNY MERRICK |
| Final | 3/17/2021 | OK for TCO | LANNY MERRICK |
| Final | 4/12/2021 | Partial Approval | LANNY MERRICK |