1821 S CRESCENT HEIGHTS BLVD 90035

Certificate Information: 1821 S CRESCENT HEIGHTS BLVD 90035

Application / Permit
19016-20000-22750
Plan Check / Job No.
B19VN12276
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-3" X 20'-2") DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 8/29/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2019 APPLICANT
Assigned to Plan Check Engineer 7/24/2019 RAPHAEL ROSAS
Corrections Issued 7/24/2019 RAPHAEL ROSAS
Building Plans Picked Up 8/1/2019 APPLICANT
Plan Check Approved 8/13/2019 RAPHAEL ROSAS
Issued 8/29/2019 LADBS
CofO in Progress 3/1/2021 JOSEPH MCGARRY
Permit Finaled 3/6/2021 DEROLD HAUFF
CofO Issued 3/6/2021 DEROLD HAUFF
Permit Finaled 3/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/6/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/6/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/6/2019 LEE GUILBEAUX
Sewer availability Cleared 8/6/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/6/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/8/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 9/8/2020 Partial Approval DAVID CHAN
ELECTRICAL-Rough 9/29/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 9/29/2020 Partial Approval DAVID CHAN
HVAC-Rough 10/19/2020 Approved DAVID CHAN
Wood Frame 10/19/2020 Conditional Approval DAVID CHAN
BUILDING-Rough-Frame 10/23/2020 Conditional Approval DAVID CHAN
Green Building Rough 10/23/2020 Approved DAVID CHAN
METHANE-Rough 10/23/2020 Approved DAVID CHAN
Drywall Nailing 11/4/2020 Approved DAVID CHAN
Interior/Exterior Lathing 11/4/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 11/25/2020 Partial Approval DAVID CHAN
Sewer 12/31/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 1/26/2021 Approved DAVID FEILER
Final 1/26/2021 Corrections Issued DAVID FEILER
Green Building Final 1/26/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 1/26/2021 SGSOV Not Ready DAVID FEILER
Smoke Detectors 1/26/2021 Approved DAVID FEILER
Final 2/19/2021 Corrections Issued JOSEPH MCGARRY
Green Building Final 2/19/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 2/19/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 2/19/2021 Approved JOSEPH MCGARRY
Final 2/25/2021 OK to Issue CofO JOSEPH MCGARRY