6353 N VAN NUYS BLVD 91401
Certificate Information: 6353 N VAN NUYS BLVD 91401
- Application / Permit
- 19016-20000-22260
- Plan Check / Job No.
- B19VN12055
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- NONSTRUCT INT REMODEL AND CHANGE OF USE FROM EX RETAIL STORE TO BANQUET HALL. SEE COMMENTS. <NFPA-13 FIRE SPRINKLER THRU-OUT>
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | HAYATO TSUCHIYA |
| Corrections Issued | 8/12/2019 | HAYATO TSUCHIYA |
| Quality Review Completed | 8/13/2019 | ABDUL CHEGENI |
| Disabled Access Plans Picked Up | 8/13/2019 | APPLICANT |
| Applicant returned to address corrections | 6/2/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 8/19/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/13/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 10/20/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/2/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 12/9/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 12/10/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 2/22/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| Issued | 3/3/2022 | APPLICANT |
| CofO in Progress | 11/1/2022 | CAMERON CHABAN |
| CofO Issued | 11/2/2022 | JEFFREY DURAN |
| Permit Finaled | 11/2/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/19/2019 | RINA LARA |
| CPC | Cleared | 9/19/2019 | RINA LARA |
| Miscellaneous | Cleared | 9/19/2019 | RINA LARA |
| Miscellaneous | Cleared | 9/19/2019 | RINA LARA |
| ZA Case | Cleared | 9/19/2019 | RINA LARA |
| ZI | Cleared | 9/19/2019 | RINA LARA |
| ZI | Cleared | 9/19/2019 | RINA LARA |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/24/2020 | ADRIAN CASTRO |
| DAS Clearance | Cleared | 12/17/2020 | HAYATO TSUCHIYA |
| Fire Marshall Fire Life Safety | Cleared | 7/30/2021 | VIDAL GARCIA |
| Food establishment approval | Cleared | 12/10/2021 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 2/3/2022 | PAWAN VERMA |
Contact Information
| Contractor | Ideal Builders Group; Lic. No.: 944360-B | 15448 LEMAC STREET VAN NUYS, CA 91406 |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 3/10/2022 | Partial Approval | CAMERON CHABAN |
| Drywall Nailing | 3/22/2022 | Partial Approval | CAMERON CHABAN |
| Final | 8/24/2022 | Partial Inspection | CAMERON CHABAN |
| Reinforced Concrete Frame | 8/24/2022 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Approved | CAMERON CHABAN |
| Smoke Detectors | 8/24/2022 | Approved | CAMERON CHABAN |
| Final | 10/21/2022 | Partial Inspection | CAMERON CHABAN |
| Final | 11/1/2022 | OK to Issue CofO | CAMERON CHABAN |