4905 N BILOXI AVE 91601
Certificate Information: 4905 N BILOXI AVE 91601
- Application / Permit
- 19016-20000-22105
- Plan Check / Job No.
- B19VN11973
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage into an Accessory Dwelling Unit per AB 494 & SB 229
- Permit Issued
- Issued on 10/30/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2019 | ANGELICA DAVE |
| Corrections Issued | 7/19/2019 | ANGELICA DAVE |
| Plan Check Approved | 7/23/2019 | PINANK PATEL |
| Issued | 10/30/2020 | APPLICANT |
| CofO in Progress | 5/5/2021 | DANIEL DREW |
| CofO Issued | 8/7/2021 | MICHAEL SMITH |
| Permit Finaled | 8/7/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 7/19/2019 | MARKOS PEREZ-BRAN |
Contact Information
| Architect | Agaian,, Raffi; Lic. No.: C32156 | 2234 DEL MAR ROAD UNIT # 1 MONTROSE, CA 91020 |
| Contractor | New Generation Home Improvements Inc; Lic. No.: 938552-B | 5805 WHITE OAK AVE #18431 ENCINO, CA 91416 |
| Engineer | Melendrez,, Edgar P; Lic. No.: C64146 | 11251 PIONEER BLVD APT A-8 NORWALK, CA 90650 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/10/2020 | Partial Approval | DANIEL DREW |
| Sewer | 11/10/2020 | Approved | DANIEL DREW |
| Underground Mechanical | 11/10/2020 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 11/19/2020 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 12/10/2020 | Partial Approval | DANIEL DREW |
| ELECTRICAL-Rough | 1/19/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Approved | DANIEL DREW |
| Green Building Rough | 1/19/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 1/19/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 1/19/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 1/26/2021 | Approved | DANIEL DREW |
| Green Building Rough | 1/26/2021 | Approved | DANIEL DREW |
| Insulation | 1/26/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 1/26/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 2/4/2021 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 2/4/2021 | Partial Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 2/4/2021 | Partial Inspection | THOMAS FINNILA |
| Wood Frame | 2/4/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/10/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 2/10/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 2/16/2021 | Approved | DANIEL DREW |
| Shower Pan | 2/16/2021 | Approved | DANIEL DREW |
| Shower Pan | 2/23/2021 | Approved | DANIEL DREW |
| Final | 4/22/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 4/22/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 4/22/2021 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 4/22/2021 | Approved | DANIEL DREW |
| Final | 5/5/2021 | OK to Issue CofO | DANIEL DREW |