4905 N BILOXI AVE 91601

Certificate Information: 4905 N BILOXI AVE 91601

Application / Permit
19016-20000-22105
Plan Check / Job No.
B19VN11973
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage into an Accessory Dwelling Unit per AB 494 & SB 229
Permit Issued
Issued on 10/30/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2019 APPLICANT
Assigned to Plan Check Engineer 7/19/2019 ANGELICA DAVE
Corrections Issued 7/19/2019 ANGELICA DAVE
Plan Check Approved 7/23/2019 PINANK PATEL
Issued 10/30/2020 APPLICANT
CofO in Progress 5/5/2021 DANIEL DREW
CofO Issued 8/7/2021 MICHAEL SMITH
Permit Finaled 8/7/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/19/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/19/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/19/2019 MARKOS PEREZ-BRAN

Contact Information

Architect Agaian,, Raffi; Lic. No.: C32156 2234 DEL MAR ROAD UNIT # 1      MONTROSE, CA 91020
Contractor New Generation Home Improvements Inc; Lic. No.: 938552-B 5805 WHITE OAK AVE #18431      ENCINO, CA 91416
Engineer Melendrez,, Edgar P; Lic. No.: C64146 11251 PIONEER BLVD APT A-8      NORWALK, CA 90650
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/10/2020 Partial Approval DANIEL DREW
Sewer 11/10/2020 Approved DANIEL DREW
Underground Mechanical 11/10/2020 Approved DANIEL DREW
Footing/Foundation/Slab 11/19/2020 Approved DANIEL DREW
Footing/Foundation/Slab 12/10/2020 Partial Approval DANIEL DREW
ELECTRICAL-Rough 1/19/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Approved DANIEL DREW
Green Building Rough 1/19/2021 Not Ready for Inspection DANIEL DREW
HVAC-Rough 1/19/2021 Approved DANIEL DREW
PLUMBING-Rough 1/19/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 1/26/2021 Approved DANIEL DREW
Green Building Rough 1/26/2021 Approved DANIEL DREW
Insulation 1/26/2021 Approved DANIEL DREW
Interior/Exterior Lathing 1/26/2021 Approved DANIEL DREW
ELECTRICAL-Rough 2/4/2021 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 2/4/2021 Partial Inspection THOMAS FINNILA
PLUMBING-Rough 2/4/2021 Partial Inspection THOMAS FINNILA
Wood Frame 2/4/2021 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 2/10/2021 Approved DANIEL DREW
HVAC-Rough 2/10/2021 Approved DANIEL DREW
Drywall Nailing 2/16/2021 Approved DANIEL DREW
Shower Pan 2/16/2021 Approved DANIEL DREW
Shower Pan 2/23/2021 Approved DANIEL DREW
Final 4/22/2021 Corrections Issued DANIEL DREW
Green Building Final 4/22/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 4/22/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 4/22/2021 Approved DANIEL DREW
Final 5/5/2021 OK to Issue CofO DANIEL DREW