254 N ASHDALE PL 90049

Certificate Information: 254 N ASHDALE PL 90049

Application / Permit
19016-20000-22007
Plan Check / Job No.
B19VN11922
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE 2'-9" x 16'-0" FROM (E) CABANA. REMODEL BATHROOM.
Permit Issued
Issued on 8/23/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 ROSENDO MEDINA
Corrections Issued 7/18/2019 ROSENDO MEDINA
Plan Check Approved 8/22/2019 SARKIS HARABEDIAN
Issued 8/23/2019 LADBS
CofO in Progress 11/25/2020 EVAN COOPER
CofO Issued 12/31/2020 VINCENT COTTON
Permit Finaled 12/31/2020 VINCENT COTTON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/22/2019 ROSENDO MEDINA

Contact Information

Contractor Owner-Builder       ,
Engineer Shakiban,, George; Lic. No.: C39908 23945 CALABASAS RD STE 101      CALABASAS, CA 91302

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/27/2019 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 10/1/2019 Partial Inspection ANTHONY MCDOWALL
Footing/Foundation/Slab 1/17/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 3/3/2020 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 4/14/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 4/14/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 4/16/2020 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 6/5/2020 Partial Approval CARLOS MATAMOROS
Final 10/23/2020 No Access for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 10/23/2020 Approved CARLOS MATAMOROS
PLUMBING-Final 10/27/2020 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 10/28/2020 SGSOV Not Ready CARLOS MATAMOROS
Final 11/24/2020 Conditional Approval EVAN COOPER
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Approved EVAN COOPER