446 N KILKEA DR 90048
Certificate Information: 446 N KILKEA DR 90048
- Application / Permit
- 19016-20000-21602
- Plan Check / Job No.
- B19VN11743
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC - CONVERT (E) 18' X 20' DET. GARAGE TO (N) ADU PER AB 494 AND SB 229 ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 11/14/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2019 | PINANK PATEL |
| Corrections Issued | 7/16/2019 | PINANK PATEL |
| Building Plans Picked Up | 7/18/2019 | APPLICANT |
| Applicant returned to address corrections | 8/5/2019 | PINANK PATEL |
| Plan Check Approved | 10/10/2019 | PINANK PATEL |
| Issued | 11/14/2019 | LADBS |
| CofO in Progress | 4/21/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 4/29/2021 | DEROLD HAUFF |
| CofO Issued | 4/29/2021 | DEROLD HAUFF |
| Permit Finaled | 4/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2019 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/1/2019 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 10/5/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/5/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 12/17/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/17/2019 | Approved | JOSEPH MCGARRY |
| Gas Test | 12/17/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/17/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 12/17/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Sewer | 12/17/2019 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 12/17/2019 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 12/17/2019 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 12/23/2019 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2019 | No Access for Inspection | JOSEPH MCGARRY |
| Gas Test | 12/23/2019 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 12/23/2019 | No Access for Inspection | JOSEPH MCGARRY |
| Insulation | 12/23/2019 | No Access for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 12/23/2019 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/30/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/21/2020 | Corrections Issued | BRAD BESCOS |
| Interior/Exterior Lathing | 1/21/2020 | Not Ready for Inspection | BRAD BESCOS |
| PLUMBING-Rough | 1/21/2020 | Approved | BRAD BESCOS |
| Wood Frame | 1/21/2020 | Partial Approval | BRAD BESCOS |
| BUILDING-Rough-Frame | 11/24/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/24/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 11/24/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 11/24/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 11/24/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| HVAC-Final | 11/24/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| METHANE-Final | 11/24/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 11/24/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/24/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/24/2020 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 11/24/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/24/2020 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/20/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 4/20/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 4/20/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/20/2021 | Approved | CHRIS CHRISTENSEN |