11327 W DELANO ST 91606

Certificate Information: 11327 W DELANO ST 91606

Application / Permit
19016-20000-21284
Plan Check / Job No.
B19VN11576
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-2" X 38'-0" GARAGE/STORAGE BUILDING TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/1/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2019 APPLICANT
Assigned to Plan Check Engineer 7/17/2019 JENNIFER LEE
Corrections Issued 7/17/2019 JENNIFER LEE
Plan Check Approved 8/28/2019 ALDO UBAU
Issued 7/1/2020 APPLICANT
CofO in Progress 6/30/2022 JOHN HAYES
Permit Finaled 8/13/2022 DANIEL ORRANTE
Permit Finaled 8/13/2022 DANIEL ORRANTE
CofO Issued 8/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/17/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 7/17/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 7/17/2019 APEKSHYA BAJRACHARYA
Construction near power lines Cleared 8/13/2019 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/23/2020 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 9/16/2020 Approved DANIEL DREW
Green Building Rough 9/16/2020 Approved DANIEL DREW
Footing/Foundation/Slab 9/28/2020 Approved DANIEL DREW
Wood Frame 9/28/2020 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Partial Approval JOHN HAYES
Wood Frame 11/16/2020 Approved DANIEL DREW
Drywall Nailing 4/22/2021 Not Ready for Inspection DANIEL DREW
Final 4/22/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 4/22/2021 Not Ready for Inspection DANIEL DREW
SGSOV-Seismic Gas S/O Valve 4/22/2021 SGSOV Not Ready DANIEL DREW
Smoke Detectors 4/22/2021 Not Ready for Inspection DANIEL DREW
Insulation 5/12/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/12/2021 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 5/12/2021 Partial Inspection MORRIS JACKSON
Drywall Nailing 5/27/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/3/2021 Approved JUSTIN HAWLEY
ELECTRICAL-Final 5/10/2022 Corrections Issued MATT KELLERMAN
Final 5/10/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 5/10/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 5/10/2022 Corrections Issued MISAEL ESPARZA
Final 5/18/2022 Not Ready for Inspection MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Approved MATT KELLERMAN
Smoke Detectors 5/18/2022 Not Ready for Inspection MATT KELLERMAN
Final 5/24/2022 Corrections Issued JACK KARGODORIAN
Smoke Detectors 5/24/2022 Approved JACK KARGODORIAN
Final 6/28/2022 OK to Issue CofO JOHN HAYES