8110 N BELLINGHAM AVE 91605

Certificate Information: 8110 N BELLINGHAM AVE 91605

Application / Permit
19016-20000-21270
Plan Check / Job No.
B19VN11568
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 18' DETACHED GARAGE AND 24' X 10' STORAGE TO ACCESSORY DWELLING UNIT PER LAMC12.22.A33(C)(E), ALL WORK PER WFPP
Permit Issued
Issued on 10/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2019 APPLICANT
Assigned to Plan Check Engineer 7/12/2019 RARES BODEA
Corrections Issued 7/12/2019 RARES BODEA
Building Plans Picked Up 7/18/2019 APPLICANT
Plan Check Approved 9/23/2020 RARES BODEA
Issued 10/6/2020 APPLICANT
CofO in Progress 10/25/2021 CHRISTOPHER DELLEFIELD
Permit Finaled 11/22/2021 MICHAEL SMITH
CofO Issued 11/22/2021 MICHAEL SMITH
Permit Finaled 11/22/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 10/27/2019 RIDWAN HARDY
Construction within easement Cleared 10/27/2019 RIDWAN HARDY
Address approval Cleared 12/11/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/11/2019 ADRIAN CASTRO
Sewer availability Cleared 12/11/2019 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/16/2020 Conditional Approval JOHN HAYES
Footing/Foundation/Slab 11/5/2020 Approved JOHN HAYES
HVAC-Rough 11/5/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 11/5/2020 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 12/3/2020 Approved JOHN HAYES
ELECTRICAL-Rough 12/3/2020 Approved JOHN HAYES
Green Building Rough 12/3/2020 Approved JOHN HAYES
HVAC-Rough 12/3/2020 Approved JOHN HAYES
PLUMBING-Rough 12/3/2020 Approved JOHN HAYES
Drywall Nailing 12/21/2020 Approved JOHN HAYES
Interior/Exterior Lathing 12/21/2020 Partial Approval JOHN HAYES
Shower Pan 12/21/2020 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 1/12/2021 Approved JOHN HAYES
Shower Pan 1/12/2021 Approved JOHN HAYES
Special/Order Compliance 1/12/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Final 10/13/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 10/13/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 10/13/2021 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 10/13/2021 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/13/2021 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 10/13/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/21/2021 Approved CHRISTOPHER DELLEFIELD
Final 10/21/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 10/21/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 10/21/2021 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/21/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/21/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
Final 10/25/2021 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 10/25/2021 Approved CHRISTOPHER DELLEFIELD