657 1/2 N WILTON PL 90004
Certificate Information: 657 1/2 N WILTON PL 90004
- Application / Permit
- 19016-20000-20699
- Plan Check / Job No.
- B19VN11279
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 17'-6" X 30'-7" GARAGE AND MAID'S ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 03/08/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 8/28/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2019 | ROSENDO MEDINA |
| Corrections Issued | 7/10/2019 | ROSENDO MEDINA |
| Building Plans Picked Up | 7/11/2019 | APPLICANT |
| Applicant returned to address corrections | 7/24/2019 | ROSENDO MEDINA |
| Plan Check Approved | 7/24/2019 | ROSENDO MEDINA |
| Issued | 8/28/2019 | LADBS |
| Refund in Progress | 12/7/2019 | MARY SUM |
| Refund Closed | 12/7/2019 | MARY SUM |
| Reactivate - Status Void | 12/7/2019 | MARY SUM |
| Issued | 6/28/2021 | LADBS |
| CofO in Progress | 6/28/2021 | JOEL WILLIAMS |
| CofO Issued | 7/2/2021 | DANIEL SANCHEZ |
| Permit Finaled | 7/2/2021 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2019 | GUILLERMO PETRA |
| Housing rent stabilization | Cleared | 7/11/2019 | MICHAEL GREGERSON |
| Sewer availability | Cleared | 7/11/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Steve'S Plumbing; Lic. No.: 649982-B | 7745 ALABAMA AVE #14 CANOGA PARK, CA 91304 |
| Engineer | Khazra,, Afshin; Lic. No.: C50250 | 22855 PAUL REVERE DR CALABASAS, CA 91302 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/17/2019 | No Access for Inspection | BENEDICT MATHIAS |
| Footing/Foundation/Slab | 10/28/2019 | Conditional Approval | BENEDICT MATHIAS |
| BUILDING-Rough-Frame | 11/20/2019 | Not Ready for Inspection | LUIS BARRALES |
| Green Building Rough | 11/20/2019 | Not Ready for Inspection | LUIS BARRALES |
| Insulation | 11/20/2019 | Not Ready for Inspection | LUIS BARRALES |
| BUILDING-Rough-Frame | 1/2/2020 | Approved | LUIS BARRALES |
| Green Building Rough | 1/2/2020 | Approved | LUIS BARRALES |
| Insulation | 1/2/2020 | Approved | LUIS BARRALES |
| Pre-Inspection | 1/2/2020 | Approved | LUIS BARRALES |
| Pre-Inspection | 1/8/2020 | Partial Approval | LUIS BARRALES |
| Interior/Exterior Lathing | 1/16/2020 | Partial Approval | ROBERT VORHIS |
| Drywall Nailing | 2/7/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 2/7/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 2/7/2020 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2020 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 2/7/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Inspection | 2/25/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Special/Order Compliance | 2/26/2020 | Corrections Issued | RAUL BARAJAS |
| Drywall Nailing | 2/16/2021 | No Access for Inspection | JOSEPH MCGARRY |
| Final | 2/16/2021 | No Access for Inspection | JOSEPH MCGARRY |
| Green Building Final | 2/16/2021 | No Access for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/16/2021 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 2/16/2021 | No Access for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/26/2021 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Special/Order Compliance | 4/27/2021 | Not Ready for Inspection | JOEL WILLIAMS |
| Drywall Nailing | 5/3/2021 | Approved | JOEL WILLIAMS |
| ELECTRICAL-Rough | 5/3/2021 | Corrections Issued | JOEL WILLIAMS |
| Final | 5/3/2021 | Not Ready for Inspection | JOEL WILLIAMS |
| Green Building Final | 5/3/2021 | Approved | JOEL WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 5/3/2021 | SGSOV Approved | JOEL WILLIAMS |
| Smoke Detectors | 5/3/2021 | Approved | JOEL WILLIAMS |
| Pre-Inspection | 6/2/2021 | Partial Approval | JOEL WILLIAMS |
| Wood Frame | 6/2/2021 | Approved | JOEL WILLIAMS |
| Final | 6/21/2021 | Not Ready for Inspection | JOEL WILLIAMS |
| ELECTRICAL-Final | 6/28/2021 | Approved | JOEL WILLIAMS |
| Final | 6/28/2021 | OK to Issue CofO | JOEL WILLIAMS |
| HVAC-Final | 6/28/2021 | Approved | JOEL WILLIAMS |
| PLUMBING-Final | 6/28/2021 | Approved | JOEL WILLIAMS |