9158-9162 N ETON AVE 91311

Certificate Information: 9158-9162 N ETON AVE 91311

Application / Permit
19016-20000-20456
Plan Check / Job No.
B19VN11163
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
change of use from mfg /office bldg to Lab./ Research center/Office /Warehouse , demo portion of (e) 2nd floor (2500 sf). restripe parking lot.
Permit Issued
Issued on 10/15/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2019 APPLICANT
Disabled Access Plans Picked Up 7/24/2019 APPLICANT
Green Plans Picked Up 7/24/2019 APPLICANT
Assigned to Plan Check Engineer 7/25/2019 CHON CHIO KUO
Corrections Issued 8/8/2019 CHON CHIO KUO
Quality Review Completed 8/15/2019 STEVEN KIM
Building Plans Picked Up 8/16/2019 APPLICANT
Applicant returned to address corrections 10/1/2019 CHON CHIO KUO
Applicant returned to address corrections 10/9/2019 CHON CHIO KUO
Plan Check Approved 10/9/2019 CHON CHIO KUO
Issued 10/15/2019 LADBS
TCO Issued (Expire Date: 09-19-2021) 3/23/2021 JEFFREY DURAN
CofO in Progress 5/7/2021 JEFFREY FULTON
Permit Finaled 6/21/2021 JEFFREY DURAN
CofO Issued 6/21/2021 JEFFREY DURAN
Permit Finaled 6/21/2021 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 9/23/2019 RINA LARA
DAS Clearance Cleared 9/23/2019 NORLITO MEDRANO
Eng Process Fee Ord 176,300 Cleared 9/26/2019 ADRIAN CASTRO
Green Code Cleared 9/26/2019 DAVID MATSON
Hydrant and Access approval Cleared 9/26/2019 GEORGE SUCHAND
Sewer availability Cleared 9/26/2019 ADRIAN CASTRO
Internal circulation Cleared 10/1/2019 ALBERT ISAGULIAN
Prkng lot landscape/Water mgmt Cleared 10/1/2019 HERMINIGILDO AGUSTIN
Sewer availability Cleared 10/3/2019 JOHN LIN

Contact Information

Architect Musser,, Raymond Lee; Lic. No.: C21168 196 CAMINO RUIZ      CAMARILLO, CA 93012
Contractor West America Construction Corporation; Lic. No.: 729556-B 2444 WILSHIRE BLVD #402      SANTA MONICA, CA 90403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 7/13/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/13/2020 Partial Inspection JEFFREY FULTON
Insulation 7/16/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/28/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/11/2020 Approved JEFFREY FULTON
Light Gage Steel Frame 8/11/2020 Approved JEFFREY FULTON
Final 12/16/2020 Not Ready for Inspection JEFFREY FULTON
Green Building Final 12/16/2020 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 12/16/2020 Approved JEFFREY FULTON
Reinforced Masonry Frame 12/16/2020 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 12/16/2020 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 12/16/2020 Approved JEFFREY FULTON
Final 3/19/2021 Partial Inspection JEFFREY FULTON
Green Building Final 3/19/2021 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/19/2021 SGSOV Approved JEFFREY FULTON
Final 5/7/2021 OK to Issue CofO JEFFREY FULTON