4391 N IRVINE AVE UNIT #3 91604
Certificate Information: 4391 N IRVINE AVE UNIT #3 91604
- Application / Permit
- 19016-20000-20344
- Plan Check / Job No.
- B19VN11113
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- INTERIOR REMODEL TO (E) UNIT TO REMODEL KITCHEN AND REPLACE STAIRCASE HANDRAIL AT 1ST FLOOR REMODEL MASTER CLOSET MASTER BATHROOM , ADD CLOSET, REPLACE STAIRCASE HANDRAIL AND CONVERT (E) 6' X 5'6" IRREGULAR SHAPED PORTION OF CEILING TO PORTION OF MASTER BEDROOM AT 2ND FLOOR , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Valley
- Current Status
- Issued on 8/25/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | RARES BODEA |
| Corrections Issued | 7/30/2019 | RARES BODEA |
| Quality Review Completed | 8/1/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 8/7/2019 | APPLICANT |
| Plan Check Approved | 8/22/2019 | RARES BODEA |
| Issued | 8/25/2022 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Priam Construction Inc; Lic. No.: 942581-B | 17072 KINGSBURY STREET GRANADA HILLS, CA 91344 |
| Engineer | Hajdari,, Gentjan; Lic. No.: C88031 | 157 S LOS ROBLES AVE 12 PASADENA, CA 91101 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 11/17/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 11/17/2022 | Corrections Issued | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2023 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 2/28/2023 | Approved | ROBERT DAVIS |
| Special/Order Compliance | 2/28/2023 | Partial Approval | STEVEN LEVITT |
| Wood Frame | 2/28/2023 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 3/1/2023 | Approved | ROBERT DAVIS |
| Insulation | 3/1/2023 | Approved | ROBERT DAVIS |
| Special/Order Compliance | 3/1/2023 | Partial Approval | STEVEN LEVITT |
| Wood Frame | 3/1/2023 | Approved | ROBERT DAVIS |
| Drywall Nailing | 3/7/2023 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 3/14/2023 | Approved | ROBERT DAVIS |
| Final | 9/8/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Footing/Foundation/Slab | 9/8/2023 | Approved | ROBERT DAVIS |
| Green Building Final | 9/8/2023 | Approved | ROBERT DAVIS |
| Smoke Detectors | 9/8/2023 | Approved | ROBERT DAVIS |
| Wood Frame | 9/8/2023 | Approved | ROBERT DAVIS |
| Final | 9/14/2023 | Not Ready for Inspection | ROBERT DAVIS |