7930-7932 N COZYCROFT AVE 91306
Certificate Information: 7930-7932 N COZYCROFT AVE 91306
- Application / Permit
- 19016-20000-19715
- Plan Check / Job No.
- B19VN10799
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 18'-3" X 18'-6" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/19/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2019 | JENNIFER LEE |
| Corrections Issued | 7/10/2019 | JENNIFER LEE |
| Plan Check Approved | 7/19/2019 | ANGELICA MARTINEZ |
| Issued | 7/19/2019 | LADBS |
| CofO in Progress | 2/11/2022 | STEVEN BACK |
| Permit Finaled | 2/15/2022 | JOHN JANSON |
| CofO Issued | 2/15/2022 | JOHN JANSON |
| Permit Finaled | 2/15/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2019 | JULIUS GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2019 | JULIUS GARCIA |
| Sewer availability | Cleared | 7/19/2019 | JULIUS GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/23/2019 | Approved | HENRY KIM |
| Pre-Inspection | 6/11/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 9/21/2021 | Approved | HENRY KIM |
| PLUMBING-Rough | 9/21/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 10/8/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 10/8/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 10/8/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 11/9/2021 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 11/9/2021 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 11/16/2021 | Approved | STEVEN BACK |
| Green Building Rough | 11/16/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 11/16/2021 | Approved | STEVEN BACK |
| Insulation | 11/16/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 11/16/2021 | Partial Inspection | STEVEN BACK |
| Shower Pan | 11/16/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 11/23/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/23/2021 | Approved | MORRIS JACKSON |
| Final | 1/19/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 1/19/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 1/19/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 1/19/2022 | Approved | STEVEN BACK |
| Final | 2/2/2022 | Corrections Issued | STEVEN BACK |
| Final | 2/11/2022 | OK to Issue CofO | STEVEN BACK |