9533-9535 N RUBIO AVE 91343
Certificate Information: 9533-9535 N RUBIO AVE 91343
- Application / Permit
- 19016-20000-19390
- Plan Check / Job No.
- B19VN10614
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert irregular shaped 17.25' x 6' (88 SF) portion of attached garage to laundry room and remaining garage area to accessory dwelling unit per AB494 & SB229. All works are per design
- Permit Issued
- Issued on 7/16/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2019 | ALDOUS CHIC |
| Corrections Issued | 6/26/2019 | ALDOUS CHIC |
| Plan Check Approved | 7/2/2019 | SARKIS HARABEDIAN |
| Issued | 7/16/2019 | LADBS |
| CofO in Progress | 10/28/2022 | RAUL OLAGI |
| CofO Issued | 11/1/2022 | MICHAEL SMITH |
| Permit Finaled | 11/1/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/26/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/26/2019 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 7/2/2019 | ALDOUS CHIC |
Contact Information
| Architect | Tohill,, Kevin Patrick; Lic. No.: C32787 | 3790 LIGHTNING RIDGE WAY SIMI VALLEY, CA 93063 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/13/2020 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 3/26/2020 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/28/2020 | Approved | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 6/8/2020 | Approved | PIERRE VEGA |
| Wood Frame | 6/8/2020 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/30/2021 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/30/2021 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/22/2021 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/28/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 10/28/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 10/28/2022 | Approved | RAUL OLAGI |
| Final | 10/28/2022 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 10/28/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 10/28/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 10/28/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 10/28/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 10/28/2022 | Approved | RAUL OLAGI |