16615 W LOS ALIMOS ST 91344

Certificate Information: 16615 W LOS ALIMOS ST 91344

Application / Permit
19016-20000-19114
Plan Check / Job No.
B19VN10500
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 8/30/2021
Issuing Office
Current Status
CofO Issued on 6/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 JENNIFER LEE
Corrections Issued 6/27/2019 JENNIFER LEE
Applicant returned to address corrections 12/14/2020 JENNIFER LEE
Plan Check Approved 8/17/2021 JENNIFER LEE
Issued 8/30/2021 APPLICANT
Building Plans Picked Up 8/31/2021 APPLICANT
CofO in Progress 5/31/2023 JAVIER RAMOS JR
CofO Issued 6/5/2023 MICHAEL SMITH
Permit Finaled 6/5/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/8/2019 GUILLERMO PETRA
Sewer availability Cleared 7/8/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/5/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2021 Not Ready for Inspection JOHN HAYES
Pre-Inspection 10/20/2021 Partial Inspection MARK JOHNSON
Deputy Drilled-In Anchors 10/27/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 10/28/2021 Corrections Issued MARK JOHNSON
Excavation/Setback/Form/Re-Bar 11/1/2021 Approved MARK JOHNSON
Footing/Foundation/Slab 11/1/2021 Approved MARK JOHNSON
PLUMBING-Rough 11/10/2021 Corrections Issued MARK JOHNSON
PLUMBING-Rough 11/16/2021 Partial Approval MARK JOHNSON
Interior/Exterior Lathing 12/9/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/31/2022 Partial Inspection MICHAEL TEMPLE
Special/Order Compliance 1/31/2022 Partial Inspection MICHAEL TEMPLE
Special/Order Compliance 2/1/2022 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 2/3/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 5/13/2022 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 5/25/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 5/25/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/1/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 7/1/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 7/13/2022 Corrections Issued DEANDRE HOFFMAN
Deputy Wood Construction 7/21/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 7/26/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/26/2022 Approved JAVIER RAMOS JR
Green Building Rough 7/26/2022 Approved JAVIER RAMOS JR
HVAC-Rough 7/26/2022 Conditional Approval JAVIER RAMOS JR
Insulation 7/26/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 7/26/2022 Approved JAVIER RAMOS JR
Underground Mechanical 9/13/2022 Partial Approval JAVIER RAMOS JR
Underground Mechanical 9/14/2022 Partial Approval JAVIER RAMOS JR
Gas Test 2/24/2023 Partial Approval JAVIER RAMOS JR
Drywall Nailing 4/14/2023 Approved JAVIER RAMOS JR
Final 4/14/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/14/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/14/2023 Approved JAVIER RAMOS JR
Final 5/31/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 5/31/2023 Approved JAVIER RAMOS JR