7239 N LOUISE AVE 91406
Certificate Information: 7239 N LOUISE AVE 91406
- Application / Permit
- 19016-20000-18903
- Plan Check / Job No.
- B19VN10390
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) ONE CAR GARAGE INTO (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229. WORK PER LA STD WFPP.
- Permit Issued
- Issued on 6/24/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 6/21/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/24/2019 | TROY DEGUZMAN |
| Issued | 6/24/2019 | LADBS |
| CofO in Progress | 12/30/2019 | JACK KARGODORIAN |
| CofO Issued | 9/29/2020 | MICHAEL SMITH |
| Permit Finaled | 9/29/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 6/21/2019 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 6/24/2019 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2019 | Partial Inspection | JACK KARGODORIAN |
| Underground Mechanical | 7/19/2019 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 7/24/2019 | Corrections Issued | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 8/30/2019 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/30/2019 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 9/9/2019 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/18/2019 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 9/18/2019 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 9/23/2019 | Approved | JACK KARGODORIAN |
| Wood Frame | 10/4/2019 | Approved | JACK KARGODORIAN |
| Insulation | 10/11/2019 | Approved | DANIEL ORRANTE |
| Insulation | 10/16/2019 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 10/21/2019 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/21/2019 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 11/25/2019 | Approved | JENNIFER RABUCHIN |
| Final | 11/25/2019 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/25/2019 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 11/25/2019 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/25/2019 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2019 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 11/25/2019 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/27/2019 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/27/2019 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/27/2019 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 11/27/2019 | Partial Approval | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/11/2019 | SGSOV Not Ready | JACK KARGODORIAN |
| Final | 12/13/2019 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 12/13/2019 | Approved | JACK KARGODORIAN |
| HVAC-Final | 12/13/2019 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2019 | SGSOV Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 12/18/2019 | Approved | JACK KARGODORIAN |
| Final | 12/30/2019 | Conditional Approval | JACK KARGODORIAN |