7708 W BECKETT ST 91042
Certificate Information: 7708 W BECKETT ST 91042
- Application / Permit
- 19016-20000-18190
- Plan Check / Job No.
- B19VN10033
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 18'5" X 16'6" OF ACCESSORY DWELLING UNIT PER AB 494 & SB 229 TO (E) GARAGE.
- Permit Issued
- Issued on 9/4/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2019 | PINANK PATEL |
| Corrections Issued | 6/17/2019 | PINANK PATEL |
| Building Plans Picked Up | 6/18/2019 | APPLICANT |
| Plan Check Approved | 9/4/2019 | PINANK PATEL |
| Issued | 9/4/2019 | LADBS |
| CofO in Progress | 9/16/2020 | BEAU COLLINS |
| CofO Issued | 10/17/2020 | MICHAEL SMITH |
| Permit Finaled | 10/17/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/19/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2019 | JOHN LIN |
| Sewer availability | Cleared | 6/19/2019 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 9/4/2019 | PINANK PATEL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/19/2019 | Not Ready for Inspection | BEAU COLLINS |
| Pre-Inspection | 9/25/2019 | Partial Inspection | BEAU COLLINS |
| Pre-Inspection | 1/6/2020 | Partial Inspection | BEAU COLLINS |
| BUILDING-Rough-Frame | 5/26/2020 | Approved | BEAU COLLINS |
| Final | 5/26/2020 | Not Ready for Inspection | BEAU COLLINS |
| Footing/Foundation/Slab | 5/26/2020 | Approved | BEAU COLLINS |
| Green Building Final | 5/26/2020 | Not Ready for Inspection | BEAU COLLINS |
| Green Building Rough | 5/26/2020 | Approved | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 5/26/2020 | SGSOV Not Ready | BEAU COLLINS |
| Smoke Detectors | 5/26/2020 | Not Ready for Inspection | BEAU COLLINS |
| Final | 7/16/2020 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 7/16/2020 | Approved | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 7/16/2020 | SGSOV Approved | BEAU COLLINS |
| Smoke Detectors | 7/16/2020 | Approved | BEAU COLLINS |
| Final | 9/16/2020 | OK to Issue CofO | BEAU COLLINS |