13936 W HUSTON ST 91423
Certificate Information: 13936 W HUSTON ST 91423
- Application / Permit
- 19016-20000-18176
- Plan Check / Job No.
- B19VN10023
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 8/4/2020
- Issuing Office
- Current Status
- CofO Issued on 7/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2019 | ANGELICA DAVE |
| Corrections Issued | 6/17/2019 | ANGELICA DAVE |
| Applicant returned to address corrections | 11/5/2019 | ANGELICA DAVE |
| Applicant returned to address corrections | 6/17/2020 | LUIS RINCON |
| Plan Check Approved | 7/20/2020 | RAPHAEL ROSAS |
| Issued | 8/4/2020 | APPLICANT |
| CofO in Progress | 5/6/2022 | MISAEL ESPARZA |
| CofO Issued | 7/6/2022 | MICHAEL SMITH |
| Permit Finaled | 7/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/17/2019 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 1/16/2020 | RIDWAN HARDY |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/12/2020 | Corrections Issued | DANIEL DREW |
| Footing/Foundation/Slab | 11/19/2020 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 12/23/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 2/3/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 2/3/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/3/2021 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 2/3/2021 | Approved | ARAM AVEDISIAN |
| Wood Frame | 2/3/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 2/24/2021 | Not Ready for Inspection | CHARLES POWELL |
| Insulation | 2/24/2021 | Not Ready for Inspection | CHARLES POWELL |
| Pre-Inspection | 3/15/2021 | Partial Inspection | DANIEL ORRANTE |
| Special/Order Compliance | 3/15/2021 | Partial Approval | CHARLES POWELL |
| Pre-Inspection | 3/24/2021 | Partial Approval | CHARLES POWELL |
| Pre-Inspection | 3/30/2021 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 5/20/2021 | Approved | CHARLES POWELL |
| HVAC-Rough | 5/20/2021 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 5/20/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 5/27/2021 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 5/27/2021 | Approved | CHARLES POWELL |
| Green Building Rough | 5/27/2021 | Not Ready for Inspection | CHARLES POWELL |
| Wood Frame | 6/3/2021 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/9/2021 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 6/9/2021 | Not Ready for Inspection | CHARLES POWELL |
| Wood Frame | 6/9/2021 | Partial Approval | CHARLES POWELL |
| Insulation | 6/11/2021 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 6/16/2021 | Not Ready for Inspection | ALAN MORELOS |
| Interior/Exterior Lathing | 6/16/2021 | Not Ready for Inspection | ALAN MORELOS |
| Drywall Nailing | 6/21/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/21/2021 | Approved | RYAN SALAZAR |
| Shower Pan | 6/21/2021 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/29/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 12/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/29/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 12/29/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 12/29/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 12/29/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/29/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 12/29/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 3/3/2022 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/3/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 3/3/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 3/3/2022 | Approved | MISAEL ESPARZA |
| HVAC-Final | 3/3/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 3/3/2022 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 3/3/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 3/3/2022 | Approved | MISAEL ESPARZA |
| Final | 3/10/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 3/10/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 3/10/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 5/5/2022 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 5/5/2022 | Approved | MISAEL ESPARZA |