7444-7446 N ASMAN AVE 91307
Certificate Information: 7444-7446 N ASMAN AVE 91307
- Application / Permit
- 19016-20000-18172
- Plan Check / Job No.
- B19VN10019
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 6/17/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2019 | ALDOUS CHIC |
| Corrections Issued | 6/17/2019 | ALDOUS CHIC |
| Plan Check Approved | 6/17/2019 | ARTIN ZARUKIAN |
| Issued | 6/17/2019 | LADBS |
| CofO in Progress | 10/1/2025 | JEFFREY HARTLINE |
| Permit Finaled | 10/2/2025 | JOHN JANSON |
| CofO Issued | 10/2/2025 | JOHN JANSON |
| Permit Finaled | 10/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 6/17/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Gaspar'S Plumbing And General Construction Inc; Lic. No.: 608149-B | 7245 SHOUP AVENUE WEST HILLS, CA 91307 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/23/2019 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 1/15/2020 | Corrections Issued | PETER FOLLING |
| Deputy Drilled-In Anchors | 1/28/2020 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 1/30/2020 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 3/16/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 3/16/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 3/16/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 3/16/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 4/21/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 4/21/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 4/21/2020 | Approved | DAVID STEPANYAN |
| Deputy Drilled-In Anchors | 7/7/2020 | Conditional Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 7/15/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 7/15/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 7/15/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 7/15/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 7/22/2020 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 7/22/2020 | Approved | DAVID STEPANYAN |
| Insulation | 7/22/2020 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 8/13/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 8/24/2020 | Partial Approval | DAVID STEPANYAN |
| Insulation | 12/9/2022 | No Access for Inspection | KRISTEN CAUSEY |
| Insulation | 12/15/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 2/1/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/1/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 2/1/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 2/1/2024 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/1/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 2/6/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 2/15/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 2/15/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/25/2024 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/22/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Final | 5/22/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Final | 5/22/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 5/22/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Final | 8/5/2024 | Approved | JEFFREY HARTLINE |
| Final | 8/5/2024 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 8/5/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 8/5/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 8/5/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 8/5/2024 | Approved | JEFFREY HARTLINE |
| Final | 9/15/2025 | Partial Approval | JEFFREY HARTLINE |
| Final | 10/1/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| HVAC-Final | 10/1/2025 | Approved | JEFFREY HARTLINE |