1226 S STEARNS DR 90035

Certificate Information: 1226 S STEARNS DR 90035

Application / Permit
19016-20000-17973
Plan Check / Job No.
B19VN09903
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING TWO CAR GARAGE TO ACCESSORY DWELLING UNIT (SEE COMMENTS)
Permit Issued
Issued on 7/1/2020
Issuing Office
Current Status
CofO Issued on 9/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Disabled Access Plans Picked Up 7/1/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 RUDOLF KINAR MELIKOFF
Corrections Issued 7/8/2019 RUDOLF KINAR MELIKOFF
Quality Review Completed 7/9/2019 STEVEN KIM
Building Plans Picked Up 7/9/2019 APPLICANT
Applicant returned to address corrections 1/17/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 5/21/2020 ALYSSA N NARCISO
Plan Check Approved 6/18/2020 ALYSSA N NARCISO
Issued 7/1/2020 APPLICANT
CofO in Progress 9/19/2022 JOSE AVILA
Permit Finaled 9/30/2022 DEROLD HAUFF
CofO Issued 9/30/2022 DEROLD HAUFF
Permit Finaled 9/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/6/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 9/6/2019 GUILLERMO PETRA
Sewer availability Cleared 9/6/2019 GUILLERMO PETRA
Miscellaneous Cleared 12/20/2019 LEE GUILBEAUX
HPOZ Cleared 1/15/2020 JONATHAN KAPLAN
ZI Cleared 1/15/2020 JONATHAN KAPLAN
Hydrant and Access approval Cleared 1/17/2020 GEORGE SUCHAND
Green Code Cleared 5/6/2020 MICHAEL AYERS
ZA Case Cleared 5/6/2020 MIGUEL GAMBOA
ZA Case Cleared 5/6/2020 MIGUEL GAMBOA
DAS Clearance Cleared 6/18/2020 NORLITO MEDRANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/23/2020 Corrections Issued DAVID CHAN
SGSOV-Seismic Gas S/O Valve 9/23/2020 SGSOV Not Ready DAVID CHAN
BUILDING-Rough-Frame 3/8/2021 Corrections Issued SCOTT FINNILA
METHANE-Rough 3/8/2021 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 4/27/2021 Corrections Issued STUART CHAPMAN
Pre-Inspection 6/2/2021 No Access for Inspection RUBEN SALAS
Pre-Inspection 6/11/2021 Partial Inspection SCOTT FINNILA
Pre-Inspection 7/12/2021 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 9/24/2021 Corrections Issued DANIEL GONZALEZ
Footing/Foundation/Slab 11/17/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 11/23/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 11/30/2021 Partial Approval JOSE AVILA
Footing/Foundation/Slab 12/6/2021 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 12/9/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 12/10/2021 No Access for Inspection JOSE AVILA
Footing/Foundation/Slab 12/16/2021 Approved JOSE AVILA
Footing/Foundation/Slab 12/17/2021 Approved JOSE AVILA
BUILDING-Rough-Frame 2/3/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 2/3/2022 Not Ready for Inspection JOSE AVILA
METHANE-Rough 2/3/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 2/3/2022 Not Ready for Inspection JOSE AVILA
METHANE-Rough 4/11/2022 No Access for Inspection JOSE AVILA
Pre-Inspection 4/11/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 4/15/2022 Partial Inspection JOSE AVILA
Pre-Inspection 4/15/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 5/5/2022 Partial Approval JOSE AVILA
METHANE-Rough 5/5/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 5/16/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/16/2022 Approved JOSE AVILA
ELECTRICAL-Rough 6/3/2022 Corrections Issued JOSE AVILA
HVAC-Rough 6/3/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 6/3/2022 Approved JOSE AVILA
HVAC-Rough 6/9/2022 Corrections Issued JOSE AVILA
METHANE-Rough 6/9/2022 Approved JOSE AVILA
ELECTRICAL-Rough 6/20/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 6/30/2022 Approved JOSE AVILA
HVAC-Rough 6/30/2022 Approved JOSE AVILA
Drywall Nailing 8/16/2022 Conditional Approval ALIZAH MAYAGOITIA
ELECTRICAL-Final 8/16/2022 Corrections Issued ALIZAH MAYAGOITIA
Final 8/16/2022 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 8/16/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 8/16/2022 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 8/16/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 8/24/2022 Approved JOSE AVILA
ELECTRICAL-Final 9/6/2022 Approved JOSE AVILA
HVAC-Final 9/6/2022 Approved JOSE AVILA
PLUMBING-Final 9/6/2022 Approved JOSE AVILA
Final 9/16/2022 OK to Issue CofO JOSE AVILA