5046 E YORK BLVD 90042
Certificate Information: 5046 E YORK BLVD 90042
- Application / Permit
- 19016-20000-17402
- Plan Check / Job No.
- B19VN09611
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- CHANGE OF USE FROM RETAIL SPACE TO GROCERY STORE
- Permit Issued
- Issued on 8/5/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 6/10/2019 | APPLICANT |
Assigned to Plan Check Engineer | 6/27/2019 | SELLA BENYAMIN |
Corrections Issued | 7/1/2019 | SELLA BENYAMIN |
Quality Review Completed | 7/2/2019 | STEVEN KIM |
Building Plans Picked Up | 7/3/2019 | APPLICANT |
Plan Check Approved | 7/26/2019 | SELLA BENYAMIN |
Issued | 8/5/2019 | LADBS |
CofO in Progress | 4/15/2020 | ERNESTO CORRAL |
CofO Issued | 5/13/2020 | TERRY HERR |
Permit Finaled | 5/13/2020 | TERRY HERR |
Permit Application Clearance Information
Address approval | Cleared | 7/3/2019 | APEKSHYA BAJRACHARYA |
Eng Process Fee Ord 176,300 | Cleared | 7/3/2019 | APEKSHYA BAJRACHARYA |
Sewer availability | Cleared | 7/3/2019 | APEKSHYA BAJRACHARYA |
DAS Clearance | Cleared | 7/12/2019 | SELLA BENYAMIN |
Food establishment approval | Cleared | 7/26/2019 | LACDHS APPROVED |
Contact Information
Contractor | Modern American Construction Inc; Lic. No.: 963454-B | 218 S AVE 63 LOS ANGELES, CA 90042 |
Inspector Information
JULIAN CAPUCETTI, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 10/4/2019 | Not Ready for Inspection | ERNESTO CORRAL |
Wood Frame | 10/4/2019 | Not Ready for Inspection | ERNESTO CORRAL |
Drywall Nailing | 12/13/2019 | Partial Inspection | ERNESTO CORRAL |
Footing/Foundation/Slab | 12/13/2019 | Approved | ERNESTO CORRAL |
Wood Frame | 12/13/2019 | Partial Inspection | ERNESTO CORRAL |
Drywall Nailing | 2/7/2020 | Partial Inspection | KATY RAMIREZ |
Wood Frame | 2/7/2020 | Partial Inspection | KATY RAMIREZ |
Special/Order Compliance | 3/12/2020 | Partial Inspection | RONALD PACHECO |
Final | 3/31/2020 | Partial Inspection | ERNESTO CORRAL |
SGSOV-Seismic Gas S/O Valve | 3/31/2020 | SGSOV Approved | ERNESTO CORRAL |
Smoke Detectors | 3/31/2020 | Approved | ERNESTO CORRAL |
Final | 4/1/2020 | Partial Inspection | ERNESTO CORRAL |
Special/Order Compliance | 4/2/2020 | Approved | ERNESTO CORRAL |
Special/Order Compliance | 4/9/2020 | Not Ready for Inspection | RONALD PACHECO |
Final | 4/15/2020 | OK to Issue CofO | ERNESTO CORRAL |