135 E WATERVIEW ST 90293

Certificate Information: 135 E WATERVIEW ST 90293

Application / Permit
19016-20000-14573
Plan Check / Job No.
B19VN08065
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL & CONVERT(E) ENCLOSE SPACE TO AN OPEN BALCONY TO (E) 3 STORY SINGLE FAMILY DWELLING (NO INCREASE IN SF). WORK PER ENGINEER. "COMPLY WITH DEPARTMENT ORDER effective date 05/18/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 1/29/2020
Issuing Office
Metro
Current Status
Permit Finaled on 11/10/2021

Permit Application Status History

Submitted 5/16/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 TROY DEGUZMAN
Corrections Issued 7/1/2019 TROY DEGUZMAN
Quality Review Completed 7/10/2019 CHON CHIO KUO
Building Plans Picked Up 7/22/2019 APPLICANT
Applicant returned to address corrections 9/13/2019 TROY DEGUZMAN
Applicant returned to address corrections 10/1/2019 TROY DEGUZMAN
Applicant returned to address corrections 11/6/2019 TROY DEGUZMAN
Applicant returned to address corrections 1/3/2020 TROY DEGUZMAN
Applicant returned to address corrections 1/10/2020 TROY DEGUZMAN
Plan Check Approved 1/24/2020 TROY DEGUZMAN
Issued 1/29/2020 LADBS
Permit Finaled 11/9/2021 MARIAN PODPORA

Permit Application Clearance Information

GPI Written Notices Cleared 7/1/2019 TROY DEGUZMAN
Grading Pre-Inspection Cleared 7/1/2019 TROY DEGUZMAN
Green Code Cleared 7/31/2019 MICHAEL AYERS
Eng Process Fee Ord 176,300 Cleared 8/26/2019 JEANIE LAM
Roof/Waste drainage to street Cleared 8/26/2019 JEANIE LAM
Sewer availability Cleared 8/26/2019 JEANIE LAM
ZA Case Cleared 8/26/2019 ANNA VAN
Coastal Zone Cleared 1/10/2020 STEVEN WECHSLER

Contact Information

Architect Nardi,, Norberto F; Lic. No.: C28794 805 S SHAMROCK AVENUE      MONROVIA, CA 91016
Contractor Owner-Builder       ,
Engineer Lothrop,, Shawn Duane; Lic. No.: S5627 40810 COUNTY CENTER DR STE 110      TEMECULA, CA 92563

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2020 Approved MARIAN PODPORA
Footing/Foundation/Slab 3/3/2020 Partial Approval MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 4/1/2020 Partial Approval MARIAN PODPORA
Footing/Foundation/Slab 4/1/2020 Partial Approval MARIAN PODPORA
Reinforced Concrete Frame 4/14/2020 Approved MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Not Ready for Inspection MARIAN PODPORA
Interior/Exterior Lathing 6/3/2020 Approved MARIAN PODPORA
ELECTRICAL-Rough 6/10/2020 Partial Approval MARIAN PODPORA
Deck 12/4/2020 Corrections Issued JOHN MATTILLO
BUILDING-Rough-Frame 1/29/2021 Approved MARIAN PODPORA
Final 1/29/2021 Not Ready for Inspection MARIAN PODPORA
METHANE-Final 1/29/2021 Approved MARIAN PODPORA
METHANE-Rough 1/29/2021 Approved MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 1/29/2021 SGSOV Approved MARIAN PODPORA
Smoke Detectors 1/29/2021 Conditional Approval MARIAN PODPORA
Final 4/9/2021 Not Ready for Inspection MARIAN PODPORA
HVAC-Final 4/9/2021 Not Ready for Inspection MARIAN PODPORA
PLUMBING-Final 4/9/2021 Not Ready for Inspection MARIAN PODPORA
Smoke Detectors 4/9/2021 Approved MARIAN PODPORA
Final 6/15/2021 Corrections Issued MARIAN PODPORA
Final 7/29/2021 Not Ready for Inspection MARIAN PODPORA
ELECTRICAL-Final 8/4/2021 Approved MARIAN PODPORA
ELECTRICAL-Rough 8/4/2021 Approved MARIAN PODPORA
Final 8/4/2021 Not Ready for Inspection MARIAN PODPORA
Gas Test 8/4/2021 Corrections Issued MARIAN PODPORA
HVAC-Final 8/4/2021 Not Ready for Inspection MARIAN PODPORA
HVAC-Rough 8/4/2021 Not Ready for Inspection MARIAN PODPORA
PLUMBING-Final 8/4/2021 Not Ready for Inspection MARIAN PODPORA
PLUMBING-Rough 8/4/2021 Approved MARIAN PODPORA
Rough-Elec/Plmb/HVAC 8/4/2021 Corrections Issued MARIAN PODPORA
Final 8/17/2021 Corrections Issued MARIAN PODPORA
Final 8/23/2021 Not Ready for Inspection MARIAN PODPORA
Gas Test 8/23/2021 Approved MARIAN PODPORA
Final 11/9/2021 Permit Finaled MARIAN PODPORA