121 N WILTON PL 90004
Certificate Information: 121 N WILTON PL 90004
- Application / Permit
- 19016-20000-14085
- Plan Check / Job No.
- B19VN07772
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 16' X 18' DET. GARAGE TO (N) ADU PER AB 494 AND SB 229 ACCESSORY DWELLING UNIT; "COMPLY WITH DEPARTMENT ORDER effective date 03/08/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 9/5/2019
- Issuing Office
- Metro
- Current Status
- Issued on 9/5/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2019 | PINANK PATEL |
| Corrections Issued | 5/13/2019 | PINANK PATEL |
| Building Plans Picked Up | 5/15/2019 | APPLICANT |
| Plan Check Approved | 5/29/2019 | PINANK PATEL |
| Issued | 9/5/2019 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/15/2019 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/15/2019 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 5/15/2019 | LEE GUILBEAUX |
| City Hist. Cultural Monument | Cleared | 5/20/2019 | MELISSA JONES |
| Historic monument | Cleared | 5/20/2019 | MELISSA JONES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/17/2019 | Corrections Issued | BENEDICT MATHIAS |
| PLUMBING-Rough | 12/2/2019 | Corrections Issued | BENEDICT MATHIAS |
| PLUMBING-Rough | 12/30/2019 | Corrections Issued | JOHN TCHANG |
| Excavation/Setback/Form/Re-Bar | 1/14/2020 | Approved | BENEDICT MATHIAS |
| BUILDING-Rough-Frame | 1/29/2020 | Conditional Approval | BENEDICT MATHIAS |
| Green Building Rough | 1/29/2020 | Not Ready for Inspection | BENEDICT MATHIAS |
| Excavation/Setback/Form/Re-Bar | 1/31/2020 | Approved | BENEDICT MATHIAS |
| HVAC-Rough | 1/31/2020 | Corrections Issued | BENEDICT MATHIAS |
| Sewer | 1/31/2020 | Approved | BENEDICT MATHIAS |
| ELECTRICAL-Rough | 2/19/2020 | Corrections Issued | EDDY ARDESSI |
| PLUMBING-Rough | 2/19/2020 | Corrections Issued | EDDY ARDESSI |
| Drywall Nailing | 4/9/2020 | Corrections Issued | EDDY ARDESSI |
| Drywall Nailing | 5/5/2020 | Approved | GORDON ZUBER |
| ELECTRICAL-Rough | 5/5/2020 | Approved | EDDY ARDESSI |
| HVAC-Rough | 5/5/2020 | Approved | EDDY ARDESSI |
| Interior/Exterior Lathing | 5/5/2020 | Approved | GORDON ZUBER |
| PLUMBING-Rough | 5/5/2020 | Approved | EDDY ARDESSI |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2020 | Approved | EDDY ARDESSI |
| Insulation | 9/10/2020 | Approved | EDDY ARDESSI |
| Wood Frame | 9/10/2020 | Approved | EDDY ARDESSI |
| Underground Mechanical | 11/12/2020 | Approved | EDDY ARDESSI |
| Drywall Nailing | 1/13/2021 | Approved | EDDY ARDESSI |
| ELECTRICAL-Rough | 1/13/2021 | Approved | EDDY ARDESSI |
| Shower Pan | 1/13/2021 | Approved | EDDY ARDESSI |
| BUILDING-Rough-Frame | 5/6/2021 | Approved | JOEL WILLIAMS |
| ELECTRICAL-Final | 5/6/2021 | Approved | JOEL WILLIAMS |
| Final | 5/6/2021 | Conditional Approval | JOEL WILLIAMS |
| Green Building Final | 5/6/2021 | Approved | JOEL WILLIAMS |
| Green Building Rough | 5/6/2021 | Approved | JOEL WILLIAMS |
| HVAC-Final | 5/6/2021 | Approved | JOEL WILLIAMS |
| PLUMBING-Final | 5/6/2021 | Approved | JOEL WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Approved | JOEL WILLIAMS |
| Smoke Detectors | 5/6/2021 | Approved | JOEL WILLIAMS |