3914 S ALLA ROAD 90066
Certificate Information: 3914 S ALLA ROAD 90066
- Application / Permit
- 19016-20000-13577
- Plan Check / Job No.
- B19VN07503
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE/RECREATION ROOM TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 6/27/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2019 | ALDOUS CHIC |
| Corrections Issued | 5/8/2019 | ALDOUS CHIC |
| Plan Check Approved | 5/10/2019 | ANGELICA MARTINEZ |
| Issued | 6/27/2019 | LADBS |
| CofO in Progress | 6/19/2020 | CRAIG DAVIS |
| Permit Finaled | 6/19/2020 | VINCENT COTTON |
| CofO Issued | 6/19/2020 | VINCENT COTTON |
| Permit Finaled | 6/19/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 5/8/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/8/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/25/2019 | Partial Approval | CRAIG DAVIS |
| Underground Mechanical | 11/1/2019 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 11/12/2019 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 12/6/2019 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/16/2019 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 1/22/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 1/24/2020 | Approved | CRAIG DAVIS |
| Wood Frame | 1/24/2020 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 1/31/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 2/5/2020 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 2/5/2020 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/2/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/8/2020 | Not Ready for Inspection | DAVID FEILER |
| Final | 6/8/2020 | Not Ready for Inspection | DAVID FEILER |
| Green Building Final | 6/8/2020 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 6/8/2020 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 6/8/2020 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 6/8/2020 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 6/15/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Final | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 6/15/2020 | Approved | OGANES TARAKHCHYAN |