15314 W SUNSET BLVD 90272

Certificate Information: 15314 W SUNSET BLVD 90272

Application / Permit
19016-20000-13185
Plan Check / Job No.
B19VN07322
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Bank
Work Description
TENANT IMPROVEMENTS ON THE FIRST FLOOR OF THE EXISTING BANK ONLY. CONSTUCT NEW SANITORY FACILITIES
Permit Issued
Issued on 4/26/2021
Issuing Office
Current Status
Permit Finaled on 12/13/2021

Permit Application Status History

Submitted 5/3/2019 APPLICANT
Green Plans Picked Up 5/14/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 ALBERT SERVIN
Corrections Issued 5/20/2019 RUDOLF KINAR MELIKOFF
Disabled Access Plans Picked Up 5/20/2019 APPLICANT
Quality Review Completed 5/22/2019 STEVEN KIM
Building Plans Picked Up 5/22/2019 APPLICANT
Applicant returned to address corrections 10/20/2020 ALBERT SERVIN
Plan Check Approved 11/6/2020 ALBERT SERVIN
Issued 4/26/2021 APPLICANT
Permit Finaled 12/10/2021 GRANT WOODS

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 5/24/2019 MELISSA JONES
ZA Case Cleared 5/24/2019 TOM HENRY
Address approval Cleared 5/28/2019 ELENA LOPEZ
Sewer availability Cleared 5/28/2019 ELENA LOPEZ
Specific Plan Cleared 5/28/2019 RUDOLF KINAR MELIKOFF
ZI Cleared 5/28/2019 RUDOLF KINAR MELIKOFF
Eng Process Fee Ord 176,300 Cleared 5/29/2019 LEE GUILBEAUX
Green Code Cleared 10/20/2020 MICHAEL AYERS
DAS Clearance Cleared 10/22/2020 NORLITO MEDRANO

Contact Information

Architect Vincent,, Dencio J; Lic. No.: C9229 1441 QUARTZ WAY      SAN JOSE, CA 95118
Contractor Clune Construction Company L P; Lic. No.: 732107-B 725 SOUTH FIGUEROA STREET   STE 300    LOS ANGELES, CA 90017
Engineer Thorpe,, William Howard; Lic. No.: S3866 1649 PALAU PLACE      COSTA MESA, CA 92626

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/1/2021 Partial Approval GRANT WOODS
Light Gage Steel Frame 7/13/2021 Partial Approval GRANT WOODS
Light Gage Steel Frame 7/19/2021 Partial Approval GRANT WOODS
Drywall Nailing 8/3/2021 Partial Approval GRANT WOODS
Drywall Nailing 8/11/2021 Partial Approval GRANT WOODS
Drywall Nailing 8/24/2021 Approved GRANT WOODS
T-Bar Ceiling 9/3/2021 Corrections Issued GRANT WOODS
T-Bar Ceiling 9/10/2021 Partial Approval GRANT WOODS
Light Gage Steel Frame 9/22/2021 Conditional Approval GRANT WOODS
T-Bar Ceiling 9/22/2021 Conditional Approval GRANT WOODS
Drywall Nailing 9/30/2021 Approved GRANT WOODS
T-Bar Ceiling 10/15/2021 Approved DERRICK SPENCER
Final 10/29/2021 Not Ready for Inspection GRANT WOODS
Green Building Final 10/29/2021 Approved GRANT WOODS
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved GRANT WOODS
Smoke Detectors 10/29/2021 Approved GRANT WOODS
Final 11/11/2021 Pending Review
Final 11/18/2021 Not Ready for Inspection GRANT WOODS
Final 12/7/2021 Not Ready for Inspection JOHN DODGE
Final 12/10/2021 Permit Finaled GRANT WOODS