3611 N LAUREL CANYON BLVD 91604
Certificate Information: 3611 N LAUREL CANYON BLVD 91604
- Application / Permit
- 19016-20000-13000
- Plan Check / Job No.
- B19VN07211
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF 20'-0"x 18'-3" (E) STORAGE , DRESS ROOM AND COV PATIO TO ACESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER LA STD WFPP.
- Permit Issued
- Issued on 5/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | TROY DEGUZMAN |
| Corrections Issued | 5/2/2019 | TROY DEGUZMAN |
| Building Plans Picked Up | 5/3/2019 | APPLICANT |
| Plan Check Approved | 5/20/2019 | TROY DEGUZMAN |
| Issued | 5/20/2019 | LADBS |
| CofO in Progress | 8/28/2020 | ARAM AVEDISIAN |
| CofO Issued | 1/26/2022 | MICHAEL SMITH |
| Permit Finaled | 1/26/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/9/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2019 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 5/9/2019 | JOHN LIN |
| Sewer availability | Cleared | 5/9/2019 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 5/20/2019 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2020 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/26/2020 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/8/2020 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/8/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/8/2020 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/16/2020 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 4/27/2020 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 4/27/2020 | Corrections Issued | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/5/2020 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 5/5/2020 | Approved | THOMAS FINNILA |
| Insulation | 5/11/2020 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/5/2020 | Approved | ARAM AVEDISIAN |
| Insulation | 6/5/2020 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 7/1/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/9/2020 | Corrections Issued | BEAU COLLINS |
| Interior/Exterior Lathing | 7/10/2020 | Approved | BEAU COLLINS |
| Final | 8/21/2020 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 8/21/2020 | Approved | ARAM AVEDISIAN |
| Final | 8/26/2020 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/26/2020 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 8/28/2020 | OK to Issue CofO | ARAM AVEDISIAN |